PMI Mock Follow-up 1 2023

PMI Mock Follow-up 1 2023

10th Grade

20 Qs

quiz-placeholder

Similar activities

Project Managment  1.00 vocaulary

Project Managment 1.00 vocaulary

9th - 12th Grade

20 Qs

PS Test Prep 12/27

PS Test Prep 12/27

8th - 12th Grade

20 Qs

Business Management I Vocab Practice (1.06)

Business Management I Vocab Practice (1.06)

9th - 12th Grade

16 Qs

2016 Excel - Lesson 3 & Lesson 4 Study Guide

2016 Excel - Lesson 3 & Lesson 4 Study Guide

9th - 12th Grade

21 Qs

U1 PM1 Unit 1 Review

U1 PM1 Unit 1 Review

9th - 12th Grade

21 Qs

2.01 - 2.03 PM Quizizz

2.01 - 2.03 PM Quizizz

9th - 12th Grade

15 Qs

Boat Build Concepts Quizizz PM1

Boat Build Concepts Quizizz PM1

9th - 12th Grade

20 Qs

PM1 Unit 5 Review

PM1 Unit 5 Review

9th - 12th Grade

22 Qs

PMI Mock Follow-up 1 2023

PMI Mock Follow-up 1 2023

Assessment

Quiz

Business

10th Grade

Medium

Created by

Bobbie Jones

Used 5+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager receives a suggestion for an app feature that was not a part of the original development scoping. What should be the first step taken to add it to the project scope?

Speaking with the team

Having a meeting with the clients to proceed with the change

Identify a change request

Revise the charter scope and get a reauthorization

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A development team discovered a faster way to review code without sacrificing quality. What should be done during the closing phase?

be careful to not release the secret of their find to the public

manage scope to ensure gold plating and scope creep are not occurring

Create a communications management plan and implement it

Archive the newly discovered process for future projects

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What are the main elements of a project status update? (Choose 2)

Who should be appointed to be on the change control board

What is forecast to be completed in the next time period

Who should be tasked with the scope revision processes

What has been completed within a specific time period

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which stakeholder has the ultimate signoff decision on a project and its deliverables?

Team Leader

Project Sponsor

Project Manager

Scrum Master

5.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

During a project planning session for a playground project, a group of people also want the existing blacktop to be repaved, which is not a part of the original project plan, adding this will increase the budget. What else will be affected? (choose 2)

Schedule

Quality

Scope

Time

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the range of activities reported on within a status update for a project plan?

the total of all tasks in a project

within a given period of time

the total tasks within a sprint

the time of a single sprint in a project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A sponsor wants to see a contingency plan for a projects budget. What should the contingency plan contain?

A percentage of the budget on top of the original budget

A report of actual costs in order to create buffers in the budget

A separate budget to be accessed as a reserve

You cannot have more than one budget so you would have to use reserve analysis

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?