PMI Mock Follow Up 2 23

Authored by Bobbie Jones

Business

10th Grade

Used 2+ times

PMI Mock Follow Up 2 23
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

30 questions

Show all answers

1.

MATCH QUESTION

1 min • 1 pt

Match the following

Formal, Informal, Open

Communication Types

Emails, Phone Calls, In-Person

Communication Methods

What is communicated and to whom

Communication Styles

Answer explanation

Just remember this:

M in Meetings = Method

Formal = Style for prom

what is left is

Type = To Whom

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project to put new floors in the high school is already behind schedule. Which adjustment to the project plan will have the best chance of putting the schedule back on track?

Increasing the project budget by 10%

Removing the task of laying down new entrance rugs in every room

Reduce the number of quality inspections on the flooring

Adding an additional team of workers to the project

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a project team receives a question about adding an app feature that was not part of the original scope, what should be the first thing the team does to add this to the scope?

Identify a change request

Send the change to the change review board

Make the change to the project scope

Do an impact analysis on the change

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When will a scope be changed when a new request not in the original plan is introduced?

Once you Identify the change request

After you send it to the change review board

Once the change has been approved

Immediately to please the customer

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The school is buidling a new intermediary campus, an the middle level hall and elementary hall can be build at the same time. When it comes time to hang blinds, the rooms should be painted first. Which type of dependency exists between the room and the blinds task?

start-start

finish-start

finish-finish

start-finish

Answer explanation

For more information: https://asana.com/resources/project-dependencies

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When a company wants to launch an e-commerce marketing campaign a social media marker should post an announcement for an on-going sale live, this can be due right as the marketing department pushes the web-page to go live. What type of dependency is this?

start-start

finish-start

finish-finish

start-finish

Answer explanation

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a project team determines that the 3D printer must be fixed prior to begin printing the boats, what type of dependcy exists?

start-start

finish-start

finish-finish

start-finish

Answer explanation

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?