ICM W13 Pop Quiz
Authored by Mohamad Ramly Zuhaili
Professional Development
University
Used 4+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of fillings for 4 nos. of P1 pad footing
2.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of formwork to footing bases for 4 nos. of P1 pad footing
3.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of disposal of excavated material for 4 nos. of F1 pad footing
4.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of concrete to 4 nos. of F1 footing bases
5.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of excavation for 8 nos. of F2 pad footing
6.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of formwork to sides of column stump for 8 nos. of F2 pad footing
7.
FILL IN THE BLANK QUESTION
3 mins • 10 pts
Total quantity of trench excavation for GB1, in total 5 similar GB
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?