
3-2 Construction Observation
Quiz
•
Architecture
•
University
•
Practice Problem
•
Medium
Centari Rodriguez
Used 1+ times
FREE Resource
Enhance your content in a minute
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is on site to observe the placement of a concrete drive and parking area. The specifications require that samples of fresh concrete be taken every 20 cubic yards during placement for 7-day and 28-day compression strength testing. The architect learns that over 250 yards of the 350 total yards of concrete have been placed and that the contractor has not taken or tested any samples. The project is weeks behind schedule. What should the architect require of the contractor?
Testing of the remaining concrete every 10 yards.
Additional testing of the in-place concrete after it has cured.
Removal and correction of all concrete that has already been placed.
2.
FILL IN THE BLANK QUESTION
1 min • 1 pt
Construction is 50% complete for a project. The contractor submits a change order for additional work costing $25,000, which is then approved. Other project details follow:
Original construction contract lump sum: $4,500,000
Total of previously approved change orders: $150,000
What is the amount of the new contract?
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A mixed-use commercial building with two ground-level restaurants is 35% into construction. After the slabs for the ground-level concrete floor have been poured, the contractor sends an RFI to the architect noting that the plumbing drawings show floor drains in the commercial kitchens, but the architectural drawings do not have floor drains. The contractor excluded floor drains during the slab pour, and the RFI requests that the floor drains be removed. The architect responds that plumbing code requires floor drains and submits a sketch with new floor drain locations.
After closing the RFI, the contractor submits a change order request to the architect and owner for the additional work to drill the concrete slab and retroactively add floor drains.
Who is responsible for the cost of the concrete removal and reinstallation?
Owner
Contractor
Architect
Plumbing engineer
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Construction is beginning on a previously developed property. During the pier excavation process, a drill hits an underground oil tank, exposing the soil and ground water to chemical contamination. The buried tank and potential contamination are unforeseen conditions not documented in the site survey or geotechnical report.
What steps must be taken to remediate the contamination and resume construction activities? Check the three that apply.
The contractor must stop work in the area affected by the contamination.
The contractor must promptly notify the owner and architect of the condition.
The geotechnical engineer should assume costs associated with site remediation.
The architect must provide recommendations for corrective remediation of the site.
The owner should hire a qualified expert to investigate the contamination for corrective action.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A four-story multifamily housing project is 30% into construction when the owner verbally requests that additional security gates be provided to the roof level access stair, which will require revisions to the stair landings. Shop drawings for the stairs have already been submitted to the architect for review. The contractor sends the architect an RFI for revised architectural drawings that incorporate the owner's design request.
What should the architect do first in response to the owner's request?
Issue a design add service proposal to the owner for the roof stair.
Issue a RFI response with revised stair drawings.
Issue a construction change directive to the contractor for the revised stair drawings.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A contractor is performing repairs to steel balcony guardrails on a 30-story high-rise condominium building when sparks from steel cutting damage the adjacent glass door at the first balcony repair area. The project manual requires the contractor to protect balcony floors and walls but does not specify protection of glass doors and windows. The contractor agrees to pay for the replacement of the damaged glass but submits a change order for the cost of installing plywood protection over all remaining doors and windows.
The owner argues that it is not their responsibility to pay for additional plywood protection.
How should the architect proceed?
Issue a change order for an increase in the contract duration but no increase in the contract sum.
Issue a field report directing the contractor to install plywood protection over the windows and doors.
Issue a construction change directive for additional plywood protection with no increase in the contract sum.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A temporary certificate of occupancy (TCO) is issued for a recently constructed office building. While conducting a punch list survey, the architect finds a section of an egress corridor that does not have the code-required illuminated exit sign. The architect informs the owner that the sign should be installed but the owner refuses, arguing that the contract drawings did not call for a sign in this location and the AHJ did not call for it in plan review when issuing the TCO.
What initial action should the architect take?
Document the owner's refusal in the project file and approve substantial completion.
Inform the owner in writing of the applicable code section and the necessity for the sign.
Offer to deduct the cost of the sign from the architect's construction administration fee.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
11 questions
Ceiling Finishes
Quiz
•
University
11 questions
BUILDING TECHNOLOGY 5
Quiz
•
University
13 questions
Underpinning
Quiz
•
University
10 questions
Portal Frame
Quiz
•
University
10 questions
Heritage Conservation and Technology Quiz
Quiz
•
University
12 questions
Door 1
Quiz
•
University
10 questions
Architecture
Quiz
•
University
10 questions
Drainage & Sewerage
Quiz
•
University
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
Discover more resources for Architecture
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
7 questions
Different Types of Energy
Interactive video
•
4th Grade - University
20 questions
Slopes and Slope-Intercept Form
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
7 questions
Biomolecules (Updated)
Interactive video
•
11th Grade - University
20 questions
Winter/Holiday Trivia
Quiz
•
KG - University
10 questions
WINTER WIN Time - ELA - 12/9/2025
Quiz
•
KG - University
7 questions
Human Impact on Resources
Interactive video
•
4th Grade - University
