Search Header Logo

Project Scope Management

Authored by Sas Pratama

Other

University

Used 1+ times

Project Scope Management
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

George is managing a construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the SS and FF relationships. How should George schedule these activities?

Apply both the relationships.

Select the relationship with the highest impact.

Select the SS relationship as this is more logical than the FF relationship.

Select the FF relationship as this can help meet the project deadlines.

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

As part of tracking a project, a project manager is validating the completion of project scope. He or she would measure this against:

Requirements traceability matrix

The Project Management Plan

The Project Charter

The Requirements Management Plan

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following processes is not a part of the Project Scope Management?

Create WBS

Control Quality

Control Scope

Collect Requirements

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Establishing control accounts for the work packages and a unique identifier from a code of accounts finalizes the WBS. This provides a structure for hierarchical summation of:

Schedule and requirements information

Cost and requirements information

Cost and resource information

Scope, budget and schedule information

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Uncontrolled project scope changes are often referred to as ________ .

Scope creep

Scope verification

Value Added Scope

Scope control

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

While managing a project, you have included the product acceptance criteria in the Quality Management Plan. While reviewing your plan, a senior manager asks you to reconsider this. You then realize that what you did is incorrect. Where should you place the product acceptance criteria?

Project Charter

Change control process

Project Scope Statement

Scope Verification Plan

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The Project Scope Management Knowledge Area is primarily concerned with:

Defining the scope of work that included in the project

Ensuring that the project includes all the work required, and only the work required, to complete the project

The scope of work required during the initiation phase

Defining the specifications and functionality of the work product

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?