Variations to Work Quiz PT6

Variations to Work Quiz PT6

Professional Development

10 Qs

quiz-placeholder

Similar activities

Project Management - Test

Project Management - Test

University - Professional Development

10 Qs

Case Study - Crescendo - 08.08.2020

Case Study - Crescendo - 08.08.2020

Professional Development

8 Qs

Project management 101

Project management 101

University - Professional Development

12 Qs

Flex Pay

Flex Pay

Professional Development

10 Qs

Kuehne + Nagel Induction Quiz

Kuehne + Nagel Induction Quiz

Professional Development

10 Qs

Cust Satisfaction using Neuro-Linguistic Programming

Cust Satisfaction using Neuro-Linguistic Programming

Professional Development

10 Qs

Discovery- You are the expert!

Discovery- You are the expert!

Professional Development

10 Qs

Welcome on board Team's follow up

Welcome on board Team's follow up

Professional Development

7 Qs

Variations to Work Quiz PT6

Variations to Work Quiz PT6

Assessment

Quiz

Other

Professional Development

Medium

Created by

Martin Biron

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the term 'variation' usually mean?

A change in the work environment

A modification to the original contract

A variation in the agreed contract price

A revision to the work programme

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How must any change to the agreed contract price for the work be agreed and approved by the owner before a variation order can be put into action?

Verbally

In writing

Through email communication

By a handshake agreement

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who may be brought in to rapidly resolve variation issues if there is poor communication, serious time delays or poor co-ordination on a project?

The project team

The owner of the project

An independent company

The contractor

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A problem with the installation, leading to a variation order, could typically have been identified by whom?

The customer

The project team

The contractor

The clerk of works

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If the customer suggests changes after the contract has been signed then who will have to bear the costs related to any delays or additional material and design to complete the work?

The contractor

The owner of the project

The customer

The project team

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a variation of work is caused, for example, by poor installation or lack of ability to complete a task properly, who is likely to be liable for any subsequent costs?

The customer

The project team

The contractor

The owner of the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How would you deal with a customer if they wanted a slight change of location for a boiler once it had been installed and commissioned?

Refuse the request as it goes against the agreed work

Offer to pass the information to your supervisor and wait for their response

Immediately make the change without consulting anyone

Tell the customer it is not possible to make any changes

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?