Sum provided for work or services to be executed by a Nominated Sub Contractor.

The statement above is

Provisional Sum

Prime Cost Sum

Preliminaries Sum

Drain Sump

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When there is Nominated Supplier, the Main Contractor may received

Profit and Attendance

Profit Only

Attendance Only

None of the above

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When there is Provisional Sum, the Main Contractor may received

Profit and Attendance

Profit Only

Attendance Only

None of the above

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Prime Cost sum is the money allocated for

Main Contractor

Nominated Sub Contractor

Sub Conctractor

Consultant

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

The Description show contract for

Provisional Sum

Preliminaries

Prime Cost Sum

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

The picture shows description for

Provisional Sum

Prime Cost Sum

Preliminaries Sum

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Below are example of items under Preliminaries Sum EXCEPT

hoarding

site office

insurance

site transportation

fire fighting installation

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?