1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is NOT part of S.M.A.R.T. acronym?

SPECIFIC

TECHNICAL

MEASUREABLE

ACHIEVABLE

REALISTIC

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Estimate At Completion (EAC) at the beginning of the project?

Equal to BAC

0

Not Possible to Calculate

None of the above

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a negative Cost Variance (CV) in Earned Value Management indicate?

Under Budget

Overbudget

On Budget

No Variance

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a Schedule Performance Index (SPI) of 1.0 indicate in Earned Value Management?

Ahead of Schedule

On Schedule

Behind Schedule

No Schedule Variance

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If the Planned Value (PV) is $80,000 and the Earned Value (EV) is $75,000, what is the Schedule Performance Index (SPI)?

0.75

0.94

1.25

1.33

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method is NOT used to measure Stakeholder Satisfaction?

Mood Chart/Board

Net Present Value (NPV)

Turnover Rate

Net Promoter Score (NPS)

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a burndown chart in Agile project management?

Track team member workloads

Monitor project costs

Visualize progress over time

Evaluate project risks

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?