PM Unit 4 Test

PM Unit 4 Test

12th Grade

13 Qs

quiz-placeholder

Similar activities

ORGANISMOS DEL COMERCIO EXTERIOR

ORGANISMOS DEL COMERCIO EXTERIOR

12th Grade

10 Qs

Tema 2 - Gestión Comercial

Tema 2 - Gestión Comercial

12th Grade

11 Qs

Quiz 1.1 in Entrepreneurship 12

Quiz 1.1 in Entrepreneurship 12

12th Grade

15 Qs

Small Business Enterprise

Small Business Enterprise

KG - University

10 Qs

Revamped New Hire Induction

Revamped New Hire Induction

KG - 12th Grade

15 Qs

Business Plan GTS

Business Plan GTS

12th Grade

10 Qs

Business Decision Making

Business Decision Making

11th - 12th Grade

16 Qs

Tax Basic

Tax Basic

1st - 12th Grade

10 Qs

PM Unit 4 Test

PM Unit 4 Test

Assessment

Quiz

Business

12th Grade

Practice Problem

Medium

Created by

Eric Doane

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1. The project manager and team have created the schedule for the hospital wireless network upgrade project. The schedule includes a five-day delay for the network approval before the hospital can use the upgraded network. This causes the finish date of the project to slip by five days. This hospital network project is:

A. accelerating. B. forming. C. lagging. D. leading.

a

b

c

d

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2. Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:

A. abstract dependency. B. discretionary dependency. C. external dependency. D. mandatory dependency.

a

b

c

d

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

3. Andy prefers to set up furniture before hanging window treatments for his interior design projects. This is an example of a/an:

A. abstract dependency. B. discretionary dependency. C. external dependency. D. mandatory dependency.

a

b

c

d

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

4. Due to a gasoline shortage, Ann is unable to secure the gasoline needed to fill up her tractor prior to planting. This is an example of a/an:

A. abstract dependency. B. discretionary dependency. C. external dependency. D. mandatory dependency.

a

b

c

d

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. It took Scott's team two hours to mow and edge one acre of land. He estimates that it will take his team eight hours to mow and edge four acres of land for an upcoming project. Scott's duration estimation for this project is an example of:

A. bottom-up estimating. B. parametric estimating. C. reserve analysis. D. three-point estimating.

a

b

c

d

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:

A. analogous estimating. B. parametric estimating. C. reserve analysis estimating. D. three-point estimating.

a

b

c

d

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?

A. analogous estimating B. parametric estimating C. reserve analysis D. three-point estimating

a

b

c

d

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?