Ôn tập IPM

Ôn tập IPM

1st - 5th Grade

41 Qs

quiz-placeholder

Similar activities

Project Manager Quiz Level 8

Project Manager Quiz Level 8

1st - 4th Grade

38 Qs

Revising and Editing 1

Revising and Editing 1

5th Grade

45 Qs

English Grammar Form 1  BK Tuition

English Grammar Form 1 BK Tuition

5th Grade

40 Qs

Sea Animals Project 2

Sea Animals Project 2

4th - 6th Grade

40 Qs

Saving The Sea Animals Project.

Saving The Sea Animals Project.

4th - 6th Grade

40 Qs

Room To Grow

Room To Grow

3rd Grade

40 Qs

Pronouns -ELA 6

Pronouns -ELA 6

KG - University

45 Qs

Grade 5 end of 1st term test

Grade 5 end of 1st term test

4th - 5th Grade

40 Qs

Ôn tập IPM

Ôn tập IPM

Assessment

Quiz

English

1st - 5th Grade

Easy

Created by

Hoàng Phạm

Used 19+ times

FREE Resource

41 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

 A project's critical path is:

  1. A. The longest path connecting the start point and the finish point of a project.

  1. B. The shortest  path connecting the start point and the finish point of a project.

  1. C. The average  path connecting the start point and the finish point of a project.

  1. D. Any path connecting the start point and the finish point of a project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Some argue that the quadruple constraint is insufficient for determining the success of a project. Instead, the quadruple constraint must be considered along with:

  1. The project's efficiency as it approaches 100%.

  1. The project's ability to harm competitors.

  1. The project's potential for generating future opportunities.

  1. The project's risk in relation to its reward.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity has an optimistic time estimate of 7 days, a most likely estimate of 9 days, and a pessimistic estimate of 14 days. What is the expected duration (ET) of the activity?

  1. 9.5 days

  1. 9.6 days

  1. 9.75 days

  1. 10 days

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

 Earned Value represents:

  1. budgeted cost of work performed.

  1. budgeted cost of work scheduled.

  1. actual cost of work performed.

  1. actual time of work performed.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following project selection models is based on decisions by the top management:

  1. Operating Necessity Model

  1. Competitive Necessity Model

  1. Sacred Cow Model

  1. Numeric Model

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

 One of the disadvantages of NPV, being used in numeric project selection model, is:

  1. NPV considers the time value of money.

  1. NPV is sensitive to discount rates.

  1. NPV helps in maximizing the firm's value.

  1. NPV takes into consideration the cost of capital and the risk inherent in making projections about the future.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

 Which of the following financial criteria considers the time value of money?

  1. ROI

  1. Break-Even Point

  1. PP

  1. NPV

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?