Pre-test Resources & Procurements Management

Pre-test Resources & Procurements Management

Professional Development

10 Qs

quiz-placeholder

Similar activities

Project Management Methodologies - Assigment

Project Management Methodologies - Assigment

Professional Development

8 Qs

Team Retro 1

Team Retro 1

Professional Development

7 Qs

Quiz Lesson 4 - Topic E (Communicate and Collaborate with Stakeh

Quiz Lesson 4 - Topic E (Communicate and Collaborate with Stakeh

Professional Development

7 Qs

Project Integration Management

Project Integration Management

Professional Development

15 Qs

Leadership for New Manager

Leadership for New Manager

Professional Development

10 Qs

Tech Mastery Day 6

Tech Mastery Day 6

Professional Development

15 Qs

Review on Project Management Concepts

Review on Project Management Concepts

Professional Development

10 Qs

Schedule Management Processes - Assignment

Schedule Management Processes - Assignment

Professional Development

6 Qs

Pre-test Resources & Procurements Management

Pre-test Resources & Procurements Management

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

SG21 PMIIC

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The Plan Procurement Management process has ten outputs, including:

1. Procurement management plan

2. Procurement strategy

3. Bid documents

4. Procurement statement of work

5. Source selection criteria

6. Make-or-buy decisions

7. Change requests

8. Project documents updates

  1. 9. Organizational process assets updates

Which of the following outputs is missing from the list?

Risk report updates

Deliverables

Performance reports

Independent cost estimates

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As a result of the customer inspection of project deliverables, some of which have been procured from a vendor, the project manager realizes that several components of the project management plan should be updated.

What should the project manager do next?

Conduct a procurement audit

Update the components as necessary

Submit a change request

Begin the Close Project or Phase process

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An accounts payable manager withholds the payment for the rental of a piece of equipment. The rental company claims the money is due in full because the piece of equipment was necessary to fulfill the objectives of the statement of work defined in the contract. Further talks lead nowhere as both parties cannot come to an agreement.

What is the next step for them to take in this situation?

Attempt alternative dispute resolution

Go to court

Approach local government officials

Start direct negotiations

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is an output of the Control Procurements process?

Work performance reports

Enterprise environmental factors updates

Closed procurements

Audit reports

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have been tasked to lead a high-priority project that will involve a very large number of stakeholders. Several project team members from various functional units within the organization have been pre-assigned to the project. You are currently working on the processes necessary to acquire goods and services needed from outside the organization.

In which Project Management Knowledge Area are you currently involved?

Conduct Procurements

Project Procurement Management

Control Procurements

Project Stakeholder Management

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are leading a software development project, which requires knowledge of several programming languages. During project execution, one of the developers has been pulled out of the project by her functional manager. The manager provided you with another developer instead.

What should you do first?

Provide the new developer with an ability test

Introduce the new developer to the project sponsor

Schedule training for the new developer

Assign the developer the next user story in the backlog

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Up until now, your project team has allowed the use of flextime where project team members may take time off during regular business hours and make up the time during the evening hours or weekends. Recently, excessive use of flextime has become a roadblock as some team members are not available when needed. The team feels they should set a standard that flextime is only to be used for personal emergencies.

How should you handle this situation?

Contact the human resources department to update the corporate policies to prohibit flextime

Submit a change request to update the team charter based on the team's inputs

Discuss the issue with the team and update the team charter accordingly

Do nothing as the team has already agreed to use flextime for personal emergencies only

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?