13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does PS stand for in the context of construction procurement?

Project Supply

Procurement System

Project System

Property System

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main characteristic of the construction industry in terms of competition?

Very competitive industry

Oligopolistic competition

Monopolistic competition

Limited competition

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the 5 main key stages of the RIBA Plan of Work 2007?

Design, Construction, Handover, Maintenance, Demolition

Concept, Procurement, Construction, Completion, Post-Completion

Inception, Design Development, Construction, Handover, Use

Feasibility, Design, Construction, Handover, Use

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main objective of a procurement system in the construction industry?

To maximize profit for the contractor

To ensure timely completion of the project

To minimize the involvement of the client

To reduce the quality of the final product

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of procurement system involves the design and construction being carried out by the same main contractor?

Management Contracting System

Design and Build System

Construction Management System

Traditional Procurement System

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of the Design and Build procurement system?

Price certainty at the award of the contract

Difficulty in comparing bids

Client changes to project scope can be expensive

Client loses direct control of design quality

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main disadvantage of the Management Contracting procurement system?

Difficulty in comparing bids

Poor price certainty

Client changes to project scope can be expensive

Client loses direct control of design quality

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?