
Block 04 - Project Monitoring and Control
Authored by Lukas Meyer
Business
University
Used 5+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is estimation considered extremely difficult in project management?
Because it requires advanced mathematical skills
Because much is new and based on unverified assumptions
Because it is always based on past projects that are difficult to understand
Because it is solely dependent on the project manager's intuition
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT an estimation method commonly used in project management?
Planning poker
Multiplier method
Pareto analysis
Parametric estimation equations
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the three-point estimation technique, how is the final estimate calculated?
By averaging the the pessimistic and worst case estimates
By taking the sum of the pessimistic, optimistic, and most likely estimates
By calculating the weighted average of the pessimistic, optimistic, and most likely estimates
By selecting the most likely estimate as the final value
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT recommended as a best practice in the estimation process for project management?
Only estimate when you have
sufficient information.
Update estimates regularly and amend them if necessary.
Allow peers to review and check your estimates.
Make estimates as early as possible.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT typically considered a task of the pre-project phase in project management?
Project organization
Feasibility test
Stakeholder analysis
Budget allocation
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT typically considered a task of the planning phase in project management?
Work Breakdown Structure (WBS) creation
Conducting a post-implementation review
Developing a cost and resource plan
Conducting a risk assessment
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT typically considered a task of the execution phase in project management?
Project Management
Situation Analysis
Controlling
Documentation
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?