PMI-SH Plan and Manage Quality of Products/deliverables

Quiz
•
Professional Development
•
1st Grade
•
Hard
sudiyuwono wowo
FREE Resource
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Question
An application developer took a story card to work that read "Customer can pay using credit card". After the implementation, the functionality was rejected because the application could not accept foreign credit cards.
What should the project manager have done to avoid this issue?
Described the user story in more detail
Gathered more detailed requirement specifications from end users.
Performed iterative backlog grooming with the team
Scheduled the user story for the next iteration.
Answer explanation
The project manager should be sure to provide the vendor with a test plan and requirements traceability matrix before the testing starts. The test plan outlines the testing approach, scope, objectives, and schedule, while the requirements traceability matrix maps the requirements to the test cases to ensure that all requirements are tested. Providing these items to the vendor helps to ensure that the testing is conducted in a structured and organized manner and that all requirements are tested.
The other options are incorrect as they do not provide the necessary information for the vendor to conduct the testing effectively.
Defect reports and quality risk assessments are produced after testing is completed.
Quality risk assessments are often carried out throughout the life cycle of the project and may not be available before the testing starts.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is working with stakeholders to identify the steps that must be completed as part of a task. The project manager needs to be able to verify that team members have completed all the steps required when performing a frequently performed task.
What should the project manager use?
Flowchart
Checklist
Histogram
Facilitation
Answer explanation
The project manager should use a checklist as it is generally used in validating process steps have been implemented.
The other answer choices are incorrect. Flowcharts can only be used to outline process steps not verify that they have been conducted; histograms reflect frequency distribution and will not verify team members have completed the tasks; and facilitation is the ability to effectively guide a group event to a successful decision, solution, or conclusion.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Question
During the development of a project, the project manager noticed that results are not as good as expected. Which tool or document shows which elements are impacting the key metrics?
Pareto Chart
Run Chart
Project Charter
Histogram
Answer explanation
A Pareto Chart indicates the frequency of defects, as well as their cumulative impact and can be useful to find the defects to prioritize in order to achieve the greatest overall improvement.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Question
A project team has not been performing user acceptance tests on a deliverable because the product has been working as expected in other projects. However, after implementation, the product is not operational.
What should the project manager do to identify the source of the problem?
Review the quality metrics document.
Develop a scatter diagram.
Conduct a root cause analysis.
Perform an audit.
Answer explanation
Root cause analysis is an analytical technique used to determine the basic underlying reason that causes a variance, defect, or risk. So conduct root cause analysis is the right choice
Quality metrics document is a description of a project or product attribute and how to measure it, and is not used to identify the source of the quality problem.
A scatter diagram is a graph that shows the relationship between two variables and is used for decision making, not identifying the source of the quality problem.
An audit is the process to determine if the project activities comply with the specific procedure, which doesn't help to identify the quality problem in this case.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Question
A project manager is newly assigned to an ongoing project and determines that the quality has been consistent. There is a considerable budget for quality assurance, and other areas of the project could benefit from these funds.
What should the project manager do?
Implement a budget reduction strategy to reallocate funds.
Perform a full inspection since there is no margin for error.
Introduce sampling as a cost-effective way to ensure quality.
Keep the budget intact for now and continue monitoring.
Answer explanation
The project manager is new to the project, so it is crucial that they take time to familiarize themselves with the existing quality assurance process and the project's specific quality needs and challenges. Project quality has been consistent, and reducing the budget at this time could jeopardize the overall quality of the project. Quality assurance efforts focus on finding quality issues as soon as possible because discovering quality issues late in development would have substantial implications and could result in project failure.
The other options are incorrect.
Reducing or reallocating the existing quality assurance budget is premature and could lead to quality issues.
A full inspection is time-consuming, expensive, and unnecessary if the project manager has no reason to believe there is a problem with the quality of the project.
Sampling is inconsistent and introducing it without a thorough evaluation and planning could be risky.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company that manufactures standard equipment for municipalities needs to ensure consistency in tasks performed regularly during product assembly. What should the project manager develop to achieve this?
Estimate Activity Resources process.
Design for X (DfX) guidelines.
Quality checklists.
Subject matter expert (SME) interviews.
Answer explanation
By developing quality checklists, the project manager can ensure that tasks are performed correctly and consistently. This will help to ensure the quality of the products and the satisfaction of the customers.
The other answer choices are incorrect. The Estimate Activity Resources process is a process used to estimate the resources needed for a project; it is not specifically designed to ensure consistency in tasks. The Design for X (DfX) guidelines are guidelines used to design products that are safe, reliable, and easy to use; they are not specifically designed to ensure consistency in tasks. Subject matter expert (SME) interviews are interviews with experts in a particular field; they are not specifically designed to ensure consistency in tasks.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project has been closed and customer care needs to measure customer satisfaction with the deliverables.
What should be done next?
A.Negotiate additional contract with customer for similar service.
Schedule meeting with stakeholders and customer to discuss lessons learned.
Evaluate project deliverables and review customer feedback documents.
Audit project success by reviewing closing documentation for each project phase.
Answer explanation
Evaluate- Closure meetings are used to confirm deliverables have been accepted, validate if acceptance criteria have been met, formalize contract completion, evaluate stakeholders satisfaction, gather lessons learned, transfer project knowledge and information, and celebrate success. Customer satisfaction can be derived by referring customer feedback documents
Negotiate- Not initiated by the customer. No need to negotiate additional contract with customer
Schedule- Previously performed at project closure. As part of Project closure meeting, lessons learned can be covered
Audit- No relevance to the question, part of gate review process
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Agile Knowledge Quiz

Quiz
•
KG - 3rd Grade
15 questions
CI - Assessment(White Belt and DMAIC)

Quiz
•
1st - 3rd Grade
11 questions
PMI-SH Assess and Manage Risks

Quiz
•
1st Grade
8 questions
PMI SH - Plan and Manage Schedule

Quiz
•
1st - 3rd Grade
10 questions
Chapt2

Quiz
•
1st Grade
10 questions
Course 1- Foundations of Project Management

Quiz
•
1st - 3rd Grade
11 questions
Prep-Cast CAPM Domain#3 : Agile Framework/Methodologies

Quiz
•
1st Grade
10 questions
RLM 1

Quiz
•
KG - 5th Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade