Risk Response Strategies - Negative Risks

Risk Response Strategies - Negative Risks

4th Grade

6 Qs

quiz-placeholder

Similar activities

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

Auditing Major Projects

Auditing Major Projects

KG - Professional Development

10 Qs

Schedule Management Terms

Schedule Management Terms

4th Grade

11 Qs

Types of Contract

Types of Contract

4th Grade

7 Qs

Schedule Management Processes

Schedule Management Processes

4th Grade

7 Qs

TIP M6 Post Test

TIP M6 Post Test

KG - 6th Grade

10 Qs

Quality Vs. Grade

Quality Vs. Grade

4th Grade

7 Qs

Conflict Resolution Techniques

Conflict Resolution Techniques

4th Grade

7 Qs

Risk Response Strategies - Negative Risks

Risk Response Strategies - Negative Risks

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 12+ times

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to build a new dam in Badakhshan, there is a high risk of flooding during the rainy season, which could significantly delay construction. What should the project manager do to avoid this risk?

Proceed with construction and deal with delays as they occur

Move the construction schedule to avoid the rainy season

Purchase insurance to cover potential delays

Accept the risk and proceed without changes

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project to deliver clean drinking water in Samangan, there is a risk that the water pipes may burst due to high water pressure in certain areas. What should the project manager do to mitigate this risk?

Accept the risk and hope for the best

Use high-quality pipes designed to withstand high pressure

Transfer the risk by hiring a water management company

Avoid installing pipes in high-pressure areas

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to develop a new e-learning platform for universities in Parwan, there is a risk of cyber-attacks that could compromise student data. What should the project manager do to transfer this risk?

Enhance internal security measures

Accept the risk and monitor for breaches

Obtain cyber insurance to cover potential cyber-attacks

Avoid storing sensitive data on the platform

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to upgrade the power grid in Kapisa, there is a minor risk of temporary power outages during the transition. What should the project manager do to accept this risk?

Implement extensive safeguards to prevent outages

Transfer the risk by outsourcing the upgrade

Avoid upgrading the power grid to prevent outages

Proceed with the upgrade and plan for minor outages

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project to build a new airport in Zabul, there is a significant risk of regulatory changes that could impact project approval and implementation. What should the project manager do to escalate this risk?

Accept the risk and continue with the project as planned

Develop contingency plans for different regulatory scenarios

Bring the risk to the attention of higher management or stakeholders who can influence regulatory bodies

Avoid addressing the risk until changes occur

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to provide renewable energy solutions in Nuristan, there is a risk that the solar panels may not generate enough power during the winter months. What should the project manager do to mitigate this risk?

Use higher-efficiency solar panels and incorporate battery storage solutions


Accept the risk and proceed without changes

Transfer the risk by hiring an external energy consultant

Avoid using solar panels during the winter months