Risk Response Strategies - Negative Risks

Authored by Afghanistan Center

Professional Development

4th Grade

Used 13+ times

Risk Response Strategies - Negative Risks
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to build a new dam in Badakhshan, there is a high risk of flooding during the rainy season, which could significantly delay construction. What should the project manager do to avoid this risk?

Proceed with construction and deal with delays as they occur

Move the construction schedule to avoid the rainy season

Purchase insurance to cover potential delays

Accept the risk and proceed without changes

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project to deliver clean drinking water in Samangan, there is a risk that the water pipes may burst due to high water pressure in certain areas. What should the project manager do to mitigate this risk?

Accept the risk and hope for the best

Use high-quality pipes designed to withstand high pressure

Transfer the risk by hiring a water management company

Avoid installing pipes in high-pressure areas

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to develop a new e-learning platform for universities in Parwan, there is a risk of cyber-attacks that could compromise student data. What should the project manager do to transfer this risk?

Enhance internal security measures

Accept the risk and monitor for breaches

Obtain cyber insurance to cover potential cyber-attacks

Avoid storing sensitive data on the platform

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to upgrade the power grid in Kapisa, there is a minor risk of temporary power outages during the transition. What should the project manager do to accept this risk?

Implement extensive safeguards to prevent outages

Transfer the risk by outsourcing the upgrade

Avoid upgrading the power grid to prevent outages

Proceed with the upgrade and plan for minor outages

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project to build a new airport in Zabul, there is a significant risk of regulatory changes that could impact project approval and implementation. What should the project manager do to escalate this risk?

Accept the risk and continue with the project as planned

Develop contingency plans for different regulatory scenarios

Bring the risk to the attention of higher management or stakeholders who can influence regulatory bodies

Avoid addressing the risk until changes occur

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to provide renewable energy solutions in Nuristan, there is a risk that the solar panels may not generate enough power during the winter months. What should the project manager do to mitigate this risk?

Use higher-efficiency solar panels and incorporate battery storage solutions


Accept the risk and proceed without changes

Transfer the risk by hiring an external energy consultant

Avoid using solar panels during the winter months

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?