1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a phase in the Waterfall model?

Feasibility study

Coding

Maintenance

Deployment

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The main drawback of the Waterfall model is:

Lack of requirements gathering

Lack of testing

Lack of documentation

Lack of flexibility

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which SDLC model is best suited for projects with unclear or changing requirements?

Waterfall model

Iterative model

Spiral model

Agile model

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which SDLC model emphasizes frequent delivery of working software?

Waterfall

Iterative

Agile

Big Bang

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Agile model, the term "sprint" refers to:

A long-term project phase

A time-boxed iteration of development

A testing phase

A documentation phase

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The primary goal of the Spiral model is to:

Minimize development costs

Increase the speed of delivery

Manage risks effectively

Enhance team collaboration

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which SDLC model is user involvement crucial throughout the development process?

Waterfall

Agile

Spiral

V-Model

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?