1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Q1) What is the least cost per m³ of blended aggregate if a concrete aggregate mix must contain 31% sand, and two sources are available: the first contains 25% sand and costs $3/m³, while the second contains 40% sand and costs $4.4/m³?
$3.56/m³
$3.80/m³
$3.92/m³
$4.00/m³
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Q2) What is the total cost and total revenue for a 12-week session at a privately-owned summer camp with a capacity of 200 campers, where each camper pays $120 per week, fixed costs are $48,000, and variable costs are $80 per camper per week?
Total Cost: $192,000; Total Revenue: $288,000
Total Cost: $240,000; Total Revenue: $288,000
Total Cost: $144,000; Total Revenue: $240,000
Total Cost: $120,000; Total Revenue: $192,000
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Q3) A company decided to landscape a lot of ground and then care for it. Which of the following costs are non-recurring costs the company incur?
Fertilize grass, shrubs
Mow grass
Remove existing trees
Water grass, shrubs
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Q4) What is the average cost per car if a car manufacturer produces 10 cars every week and incurs the following costs: AED 1,000 per week for rent, AED 1,000 per week for salaries, AED 500 per week for interest, AED 100 per car for materials, AED 50 per car for wages, and AED 100 per car for power?
400 AED
450 AED
500 AED
550 AED
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Q5) What is the Power-Sizing Exponent (PSE) that should be published, given the following data: the cost of a VMIC-200 today is $100,000, the cost of a VMIC-100 10 years ago was $45,000, the VMIC equipment index today is 856, and the VMIC equipment index 10 years ago was 604?
0.65
0.43
0.58
0.70
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Q6) What is the time required to produce the 100th unit of a production run if the 1st unit took 32 minutes to produce and the learning-curve rate for production is 80%?
8.19 minutes
10.24 minutes
12.48 minutes
7.27 minutes
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Q7) What was the learning curve rate during production if 200 labor hours were required to produce the 1st unit and 60 labor hours were required to produce the 7th unit?
50%
65%
70%
80%
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?