Predictive Plan Approach - D2

Quiz
•
Business
•
University
•
Medium
Paolino Kitieu
Used 2+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In project management, when is it appropriate to use a predictive, plan-based approach?
When the project scope and objectives are well-defined and unlikely to change
When the project is complex and involves significant uncertainty
When the project is simple and routine
When the project is a one-time event
Answer explanation
A predictive, plan-based approach, also known as a waterfall model, is a traditional project management approach that is based on a detailed plan and a linear sequence of phases.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In project management, which of the following characteristics are associated with well-defined goals?
Specific, Measurable, Achievable, Relevant, and Time-bound
General, Unmeasurable, Unachievable, Irrelevant, and Not Time-bound
Specific, Unmeasurable, Unachievable, Relevant, and Time-bound
General, Measurable, Achievable, Irrelevant, and Not Time-bound
Answer explanation
Well-defined goals in project management are characterized by being Specific, Measurable, Achievable, Relevant, and Time-bound (SMART).
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following organizational structures is most suitable for a predictive, plan-based approach?
A hierarchical structure with centralized decision making
A flat structure with decentralized decision making
A matrix structure with a balance of centralized and decentralized decision making
A virtual structure with distributed teams
Answer explanation
A predictive, plan-based approach, or a waterfall model, is a traditional project management approach based on a detailed plan and a linear sequence of phases.
This approach is best suited for organizations with a hierarchical structure and centralized decision-making, where a clear chain of command and decision-making authority is clearly defined.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a predictive, plan-based approach, which of the following activities typically takes place during the execution phase?
Identifying and managing project risks
Defining and communicating project scope and objectives
Developing a detailed project schedule
Implementing and executing project tasks
Answer explanation
In a predictive, plan-based approach, or a waterfall model, the project is divided into distinct phases, such as planning, execution, and closure, with clear deliverables and milestones for each phase.
During the execution phase, the project team focuses on implementing and executing the project tasks defined in the planning phase.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In project management, when is it appropriate to use an Agile Approach?
When the project scope and objectives are well-defined and unlikely to change
When the project is complex and involves significant uncertainty
When the project is simple and routine
When the project is a one-time event
Answer explanation
An Agile approach is a flexible, iterative and incremental method of project management characterized by its ability to adapt to changing requirements, priorities and to deliver a working product incrementally.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a predictive, plan-based approach, which of the following is a key activity when developing plans and schedules?
Identifying and mitigating project risks
Defining and communicating specific, measurable, achievable, relevant, and time-bound goals and objectives
Allocating resources and assigning tasks
Creating a detailed Gantt chart
Answer explanation
Developing plans and schedules is a key activity during the planning phase in a predictive, plan-based approach, also known as a waterfall model.
A key tool used to develop plans and schedules is a Gantt chart
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a predictive, plan-based approach, which of the following is a key activity when monitoring progress?
Identifying and mitigating project risks
Defining and communicating specific, measurable, achievable, relevant, and time-bound goals and objectives
Comparing actual progress to the project plan
Creating a detailed Gantt chart or network diagram
Answer explanation
In a predictive, plan-based approach, also known as a waterfall model, monitoring progress is a key activity throughout the project, particularly during the execution phase.
This involves comparing the actual progress of the project to the project plan, to ensure that the project is on schedule and that deliverables are completed on time.
Create a free account and access millions of resources
Similar Resources on Wayground
8 questions
5 Phases of Project Management

Quiz
•
University
8 questions
Basic Concepts in Strategic Cost Management

Quiz
•
University
12 questions
Management functions

Quiz
•
University
10 questions
Strategic Management Quiz

Quiz
•
University
10 questions
Business Plan

Quiz
•
University
10 questions
Business Management

Quiz
•
University
10 questions
Introduction to Management

Quiz
•
University - Professi...
10 questions
Strategic Planning and Management Quiz

Quiz
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade