Predictive Plan Approach - 2026

Predictive Plan Approach - 2026

University

10 Qs

quiz-placeholder

Similar activities

Principles of Management Prelim Exam

Principles of Management Prelim Exam

University

14 Qs

Topic 8

Topic 8

University

12 Qs

Planificación

Planificación

University

10 Qs

Strategic Compensation Plan

Strategic Compensation Plan

University - Professional Development

15 Qs

Human Resource Management Quiz

Human Resource Management Quiz

University

15 Qs

Short-term financing

Short-term financing

University

10 Qs

Kecerdasan Bisnis Week 03

Kecerdasan Bisnis Week 03

University

10 Qs

Entrep Mind - pretest

Entrep Mind - pretest

University

15 Qs

Predictive Plan Approach - 2026

Predictive Plan Approach - 2026

Assessment

Quiz

Business

University

Practice Problem

Medium

Created by

Paolino Kitieu

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In project management, when is it appropriate to use a predictive, plan-based approach?

When the project scope and objectives are well-defined and unlikely to change

When the project is complex and involves significant uncertainty

When the project is simple and routine

When the project is a one-time event

Answer explanation

A predictive, plan-based approach, also known as a waterfall model, is a traditional project management approach that is based on a detailed plan and a linear sequence of phases.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In project management, which of the following characteristics are associated with well-defined goals?

Specific, Measurable, Achievable, Relevant, and Time-bound

General, Unmeasurable, Unachievable, Irrelevant, and Not Time-bound

Specific, Unmeasurable, Unachievable, Relevant, and Time-bound

General, Measurable, Achievable, Irrelevant, and Not Time-bound

Answer explanation

Well-defined goals in project management are characterized by being Specific, Measurable, Achievable, Relevant, and Time-bound (SMART).

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Which of the following organizational structures is most suitable for a predictive, plan-based approach?

A hierarchical structure with centralized decision making

A flat structure with decentralized decision making

A matrix structure with a balance of centralized and decentralized decision making

A virtual structure with distributed teams

Answer explanation

A predictive, plan-based approach, or a waterfall model, is a traditional project management approach based on a detailed plan and a linear sequence of phases.

This approach is best suited for organizations with a hierarchical structure and centralized decision-making, where a clear chain of command and decision-making authority is clearly defined.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a predictive, plan-based approach, which of the following activities typically takes place during the execution phase?

Identifying and managing project risks

Defining and communicating project scope and objectives

Developing a detailed project schedule

Implementing and executing project tasks

Answer explanation

In a predictive, plan-based approach, or a waterfall model, the project is divided into distinct phases, such as planning, execution, and closure, with clear deliverables and milestones for each phase.

During the execution phase, the project team focuses on implementing and executing the project tasks defined in the planning phase.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In project management, when is it appropriate to use an Agile Approach?

When the project scope and objectives are well-defined and unlikely to change

When the project is complex and involves significant uncertainty

When the project is simple and routine

When the project is a one-time event

Answer explanation

An Agile approach is a flexible, iterative and incremental method of project management characterized by its ability to adapt to changing requirements, priorities and to deliver a working product incrementally.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a predictive, plan-based approach, which of the following is a key activity when developing plans and schedules?

Identifying and mitigating project risks

Defining and communicating specific, measurable, achievable, relevant, and time-bound goals and objectives

Allocating resources and assigning tasks

Creating a detailed Gantt chart

Answer explanation

Developing plans and schedules is a key activity during the planning phase in a predictive, plan-based approach, also known as a waterfall model.

A key tool used to develop plans and schedules is a Gantt chart

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a predictive, plan-based approach, which of the following is a key activity when monitoring progress?

  • Identifying and mitigating project risks

  • Defining and communicating specific, measurable, achievable, relevant, and time-bound goals and objectives

  • Comparing actual progress to the project plan

  • Creating a detailed Gantt chart or network diagram

Answer explanation

In a predictive, plan-based approach, also known as a waterfall model, monitoring progress is a key activity throughout the project, particularly during the execution phase.

This involves comparing the actual progress of the project to the project plan, to ensure that the project is on schedule and that deliverables are completed on time.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?