Quiz Lesson 2 - Topic D (Project Approach)

Quiz Lesson 2 - Topic D (Project Approach)

Professional Development

8 Qs

quiz-placeholder

Similar activities

PreTest - Scrum Quiz

PreTest - Scrum Quiz

Professional Development

10 Qs

aXe Quiz

aXe Quiz

Professional Development

10 Qs

PM Academy Scrum Lessons - 2 History and Purpose of Scrum

PM Academy Scrum Lessons - 2 History and Purpose of Scrum

Professional Development

7 Qs

SMPC-juego-preguntas-04

SMPC-juego-preguntas-04

Professional Development

12 Qs

Simulacro SM 1

Simulacro SM 1

Professional Development

11 Qs

Agile Management SCRUM Concept 01

Agile Management SCRUM Concept 01

Professional Development

10 Qs

SA Scrum Master 6.0 L1

SA Scrum Master 6.0 L1

Professional Development

11 Qs

Scrum Team

Scrum Team

Professional Development

10 Qs

Quiz Lesson 2 - Topic D (Project Approach)

Quiz Lesson 2 - Topic D (Project Approach)

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Abdul Habib Aulfat

Used 3+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which development approach is best suited for projects where requirements are well understood at the beginning and changes are minimal?

Adaptive

Predictive

Hybrid

Incremental

Answer explanation

The predictive approach is ideal for projects with well-understood requirements and minimal changes, as it emphasizes detailed planning and a structured process, ensuring that the project stays on track and within scope.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary focus of adaptive development approaches?

Delivering predefined deliverables

Reducing project costs

Delivering value early and incorporating customer feedback

Minimizing project risks

Answer explanation

Adaptive development approaches prioritize delivering value early and incorporating customer feedback to ensure that the final product meets user needs and expectations, making it more effective than just focusing on predefined deliverables.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a characteristic of the hybrid development approach?

Combining elements of predictive and adaptive approaches

Tailoring the development approach to the project's needs

Following a strict, unchangeable plan

Incorporating customer feedback and iterative development

Answer explanation

The hybrid development approach is flexible and adapts to project needs, incorporating feedback and iterative processes. Following a strict, unchangeable plan contradicts this flexibility, making it NOT a characteristic of hybrid development.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the context of project management, what is the role of a product owner?

Managing the project schedule and budget

Facilitating team meetings and ceremonies

Representing the customer's interests and prioritizing the product backlog

Overseeing the technical development of the project

Answer explanation

The product owner represents the customer's interests by ensuring that the product backlog is prioritized according to value and needs, which is crucial for delivering a successful project outcome.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an example of a project with multiple deliveries?

A construction project delivering a single building at the end

A software project releasing updates every two weeks

A pharmaceutical project with sequential trial results and a final launch

A marketing campaign with a single launch event

Answer explanation

The correct choice is the pharmaceutical project, as it involves multiple deliveries of trial results before the final launch, demonstrating a process with several outputs, unlike the other options which focus on single deliveries.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary benefit of using an incremental development approach?

Reducing project costs

Delivering finished deliverables that can be used immediately

Minimizing project risks

Following a strict, predefined plan

Answer explanation

The primary benefit of an incremental development approach is that it allows teams to deliver finished deliverables that can be used immediately, providing value early and enabling feedback for future iterations.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which agile framework includes roles such as scrum master and product owner, and uses sprints for iterations?

Lean Six Sigma

SAFe®

ScrumTM

Prince2

Answer explanation

The ScrumTM framework includes specific roles like the scrum master and product owner, and it organizes work into time-boxed iterations called sprints, making it distinct from Lean Six Sigma, SAFe®, and Prince2.

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a sprint retrospective in Scrum?

Planning work for the next sprint

Reviewing progress and getting feedback from stakeholders

Identifying improvements to team performance and collaboration

Prioritizing items on the product backlog

Answer explanation

The sprint retrospective focuses on identifying improvements to team performance and collaboration, allowing the team to reflect on their processes and enhance their effectiveness in future sprints.