1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is being considered for a particular project that will deal exclusively with global virtual teams. He only has experience with local teams. What should he do when discussing the opportunity with the sponsor?

The project manager should point out to the sponsor that he has not had experience with global virtual teams, but discuss why he thinks he is a good fit for the project anyway.

The project manager should point out to the sponsor that he has not had experience with global virtual teams and therefore must decline the assignment

Since the project manager has managed many projects and teams, it does not make any difference that the new project involves global virtual teams. He should tell the sponsor he has the relevant experience

The project manager should avoid any conversation regarding the types of teams involved so the sponsor does not know he lacks experience in this area.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A team member assigned to the project needs two days of training to satisfactorily complete certain activities. No one else with the necessary skills is available to the project team. What is the BEST thing to do?

Ask management for additional personnel because you cannot afford the extra schedule time

Offer a bonus to the team member if he/she gets the training on his/her own time

Include training in the project management plan

Add two days to the schedule and inform management of the delay

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Conflict on project is usually caused by:

Schedules, project priorities, resource, and technical opinions

Schedules, personality, priorities, and technical opinions

Schedule, personality, priorities, and resources

Schedules, cost, priorities, and resources

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a factor in the project manager's acquiring the best resources for the project?

Activity attributes

Quantified resource requirements by activity

Project schedule

Directive of the project manager

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At a critical design review meeting for a large project, several important issues surfaced. After hearing about a major technical problem, one of the subcontractor's engineers mentions that he experienced a similar situation on another project; he has some ideas on how to solve the current problem. What type of power is the engineer using?

Referent

Formal

Manipulative

Expert

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has several teams. Team C has repeatedly missed deadlines in the past. This has caused team D to have to crash the critical path several times. As the team leader for team D, you should meet with:

The project manager and the leader of team C

The project manager and management

The project manager

The leader of team C

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The concept of Shu Ha Ri is one of ..

Obey, detach, mastery

Learning, communicating, mastery

Novice and then proficient

Follows plans and process

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?