Search Header Logo

Project Management Scenarios

Authored by Afghanistan Center

Professional Development

4th Grade

10 Questions

Used 1+ times

Project Management Scenarios
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team working in an adaptive approach is facing delays due to unforeseen risks. The project manager wants to ensure that risks are identified as early as possible and documented properly. During a risk review meeting, a team member suggests using daily stand-up meetings to capture new risks.What should the project manager do?

Use the call to verbally summarize the work status and move forward.

Use an electronic task board to give a visual representation of risks and mitigation actions.

Ask for a change in the project's budget to provide additional funding for risk resolution.

Tailor the project to use a method to make the risk identification process more formal.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a progress meeting, the project team learns about an emerging risk that could cause major delays. The project manager realizes that the risk was not documented in the risk register. What should the project manager do next?

Ask the project sponsor to apply the management reserve to cover the impact of the risk.

Ask the project sponsor to provide additional contingency funds.

Issue a change request to modify the scope, cost, and schedule accordingly.

Use the contingency reserve and assess options for risk response.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the execution of repair work, the root cause of the problem is found to be a defect in materials provided by the seller. The contract was fixed-price with no provisions for cost-sharing on defects. The seller refuses to cover the costs of repair, citing contract terms. What should the project manager do?

Negotiate with the contractor to cancel the repair work.

Negotiate the repair work with the contractor and explore cost-sharing options.

Proceed with the contractor without mentioning the defect.

Proceed with the contractor and subtract the additional repair cost from the seller’s payment.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to reduce procurement time during a bidding process, a project manager is evaluating different contracting approaches. The objective is to select a contract that ensures fairness for both the buyer and the seller. What should the project manager do?

Invite all potential bidders to a meeting.

Award the contract without negotiation.

Follow the company's bidding procedure.

Share the project objectives with all bidders.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a deployment project that affects multiple departments. Some stakeholders have not been actively involved, and the project manager is concerned that their input is lacking. What should the project manager do?

Analyze the business impact in order to reprioritize the stakeholder engagement strategy.

Request to negotiate with the vendors for a lower cost solution to increase engagement.

Ask to order new equipment immediately so there are no further delays.

Acknowledge these constraints and take them into consideration when making decisions.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team is facing communication issues with a key stakeholder who does not actively participate in meetings. The stakeholder’s input is crucial to the success of the project. What should the project manager do?

Continue to send meeting invites and assume the stakeholder will eventually join.

Schedule one-on-one discussions with the stakeholder to understand their concerns.

Escalate the issue to the sponsor and request stakeholder replacement.

Assign another team member to handle all communications with the stakeholder.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is leading an international project with stakeholders from different cultural backgrounds. Some stakeholders struggle to understand the technical jargon used in project meetings. What should the project manager do?

Continue using technical language as it is necessary for project accuracy.

Provide simplified summaries and visuals tailored to each stakeholder’s needs.

Ask the stakeholders to take additional training to understand the technical details.

Limit stakeholder involvement to only those with technical expertise.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development