851-900 Updated

851-900 Updated

4th Grade

31 Qs

quiz-placeholder

Similar activities

LUNA BEACH CLUB Engagement Survey

LUNA BEACH CLUB Engagement Survey

1st Grade - University

30 Qs

PKP

PKP

3rd - 5th Grade

26 Qs

Quiz REV111 _12 November 2024_ 1B&1K

Quiz REV111 _12 November 2024_ 1B&1K

1st Grade - University

36 Qs

Metodologías agiles

Metodologías agiles

1st - 4th Grade

28 Qs

Perkantoran for SMK

Perkantoran for SMK

1st - 5th Grade

30 Qs

1100 - 1200 Updated

1100 - 1200 Updated

4th Grade

31 Qs

G K Quiz

G K Quiz

4th Grade

35 Qs

UTS RPL 5-6-7

UTS RPL 5-6-7

KG - Professional Development

30 Qs

851-900 Updated

851-900 Updated

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 3+ times

FREE Resource

31 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

Check the change management plan

Document the issue in the scope management plan.

Conduct a team brainstorming session to resolve the issue

Check the quality management plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team. What should the project manager do first to ensure the project is compliant?

Meet with the team to discuss compliance concerns

Review the organizational process assets (OPAs) for compliance topics

Review the compliance strategy and version history

Meet with the project sponsor to discuss their compliance concerns

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity issues joining team calls during the day. What should the project manager do?

Procure tools that consume less bandwidth for internet calls.

Record the meeting to share with the team members who were unable to join.

Ask the team members to use chat tools as an alternative to calls.

Determine what the problem is and develop an action plan.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required What should the project manager do?

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to- market need?

Add resources to activities

Conduct serial activities on tasks

Increase the number of standup meetings

Perform tasks in parallel

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project. What should the project manager do?

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project. What should the project manager do?

Advise the teams to follow the company’s existing project management approach.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

Let a senior team member select the approach that is appropriate.

Insist the teams both follow either a predictive or agile approach.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?