1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The purpose of the resource allocation histogram is to:

visualize the distribution of resources over time

allocate resources to different projects

track the progress of resource usage

predict future resource needs

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Fill in the blank: The budget for 'Design' is ______.

$1,000

$500

$2,000

$750

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What task has a budget of $2,500?

Design

Remove Old Sign

Install Concrete Base

Order New Sign

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in the sign project phases?

Remove Old Sign

Approve Design

Order Sign

Assemble Sign

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Fill in the blank: The step 'Concrete Base' in the sign project takes ___ week(s).

1 week.

2 weeks.

3 weeks.

4 weeks.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which step follows 'Order Sign' in the sign project phases?

Approve Design

Assemble Sign

Install on Base

Remove Old Sign

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The purpose of using a Work Breakdown Structure (WBS) in a project is to:

organize and define the total scope of the project

allocate resources to project tasks

monitor project progress

communicate with stakeholders

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?