17/9 Critical Path Analysis (CPA) and PERT: MCQ Quiz

Authored by Rob Davies

Other

12th Grade

17/9 Critical Path Analysis (CPA) and PERT: MCQ Quiz
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does CPA stand for in project management?

Critical Project Assessment

Critical Path Analysis

Cumulative Planning Analysis

Calculated Project Approach

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What decade did Critical Path Analysis (CPA) originate from?

1930s

1940s

1950s

1960s

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary use of CPA?

To budget project costs

To visualise project timelines and dependencies

To train staff

To communicate with clients

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does PERT stand for?

Project Estimation and Resource Tracking

Project Evaluation and Review Technique

Programmed Event Resource Timeline

Performance Evaluation and Risk Tracking

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In PERT charts, what do arrows represent?

Completed phases

Activities or work

Milestones

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of tasks are not dependent on others in CPA?

Critical tasks

Slack tasks

Dependent tasks

Non-dependent tasks

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the PERT formula help calculate?

Total budget

Best estimate time

Resource needs

Team efficiency

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?