Schedule compression & Optimization - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While reviewing the project schedule in Kandahar province, the project manager decides to run two tasks in parallel that were originally planned in sequence. This decision slightly increases risk but shortens the schedule. Which technique is being used?
Fast Tracking
Crashing
Resource Smoothing
Timeline compression through sequential parallelism using dependency bypass and milestone trigger layering
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a construction project in Panjshir province, the sponsor demands earlier delivery. The project manager brings in extra labor and overtime to reduce task duration, raising costs. What schedule compression technique is being applied here?
Crashing
Fast Tracking
Resource Leveling
Output acceleration through phased staffing augmentation, labor surge adjustment, and direct cost-driven timing realignment
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A school renovation project in Sofia city in Bulgaria has limited staff availability. The manager adjusts task start times to avoid overloading resources but keeps the final delivery date unchanged. Which schedule optimization method is being used?
Resource Smoothing
Fast Tracking
Crashing
Balanced work redistribution via constraint-aware resource pacing and schedule neutrality validation
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Bamyan province, the project team discovers two non-critical tasks are starting too early. The manager adds extra lag time to allow teams to focus on higher-priority work. Which technique is this an example of?
Applying Lag
Crashing
Resource Leveling
Lead-lag strategy optimization using buffer integration, dependency extension, and timeline decongestion
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After analyzing the project network diagram in Colombo city in Sri Lanka, the scheduler focuses on shortening the tasks on the path with no float. Why is this path the focus of optimization efforts?
It is the Critical Path
It includes high-risk tasks
It contains the most resources
It's part of a dynamic activity grouping requiring phased float adjustments, stakeholder synchronization, and sequence reconciliation
Similar Resources on Wayground
10 questions
PMP Team Quiz

Quiz
•
Professional Development
10 questions
PMP PROJECT COMMUNICATIONS MANAGEMENT

Quiz
•
Professional Development
10 questions
LO1 Organisation Structures Quiz

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
8 questions
Quiz Lesson 3 - Topic H (Integrate Plans)

Quiz
•
Professional Development
7 questions
Conflict Resolution Techniques - Assignment

Quiz
•
Professional Development
10 questions
PMP PROJECT QUALITY MANAGEMENT

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade