Schedule compression & Optimization - Assignment

Schedule compression & Optimization - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

SFS Quiz All Hands

SFS Quiz All Hands

Professional Development

9 Qs

Introduction to Project Management

Introduction to Project Management

Professional Development

10 Qs

Risk 10 soal (Chapter 11)

Risk 10 soal (Chapter 11)

Professional Development

10 Qs

Cost Management Terms - Assignment

Cost Management Terms - Assignment

Professional Development

5 Qs

Ejercicios ACP REVIT

Ejercicios ACP REVIT

Professional Development

10 Qs

SG20_Test_S3_Ch4_Integration

SG20_Test_S3_Ch4_Integration

Professional Development

10 Qs

5E Model and Effective Lesson Planning

5E Model and Effective Lesson Planning

Professional Development

10 Qs

Planning for Success Part 2

Planning for Success Part 2

Professional Development

7 Qs

Schedule compression & Optimization - Assignment

Schedule compression & Optimization - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing the project schedule in Kandahar province, the project manager decides to run two tasks in parallel that were originally planned in sequence. This decision slightly increases risk but shortens the schedule. Which technique is being used?

Fast Tracking

Crashing

Resource Smoothing

Timeline compression through sequential parallelism using dependency bypass and milestone trigger layering

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a construction project in Panjshir province, the sponsor demands earlier delivery. The project manager brings in extra labor and overtime to reduce task duration, raising costs. What schedule compression technique is being applied here?

Crashing

Fast Tracking

Resource Leveling

Output acceleration through phased staffing augmentation, labor surge adjustment, and direct cost-driven timing realignment

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A school renovation project in Sofia city in Bulgaria has limited staff availability. The manager adjusts task start times to avoid overloading resources but keeps the final delivery date unchanged. Which schedule optimization method is being used?

Resource Smoothing

Fast Tracking

Crashing

Balanced work redistribution via constraint-aware resource pacing and schedule neutrality validation

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Bamyan province, the project team discovers two non-critical tasks are starting too early. The manager adds extra lag time to allow teams to focus on higher-priority work. Which technique is this an example of?

Applying Lag

Crashing

Resource Leveling

Lead-lag strategy optimization using buffer integration, dependency extension, and timeline decongestion

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After analyzing the project network diagram in Colombo city in Sri Lanka, the scheduler focuses on shortening the tasks on the path with no float. Why is this path the focus of optimization efforts?

It is the Critical Path

It includes high-risk tasks

It contains the most resources

It's part of a dynamic activity grouping requiring phased float adjustments, stakeholder synchronization, and sequence reconciliation