Estimating Techniques - Assignment

Estimating Techniques - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

FINAL QUIZ

FINAL QUIZ

Professional Development

10 Qs

Types of fuses

Types of fuses

Professional Development

10 Qs

KUIZ GLAMOROUS NIGHT TEAM ATI

KUIZ GLAMOROUS NIGHT TEAM ATI

Professional Development

10 Qs

wsn2

wsn2

Professional Development

10 Qs

SMU Design Thinking and Doing

SMU Design Thinking and Doing

Professional Development

10 Qs

المهارات الفردية (التقنية) - Module 4 - Test 1 _ الوحدة ٤ -

المهارات الفردية (التقنية) - Module 4 - Test 1 _ الوحدة ٤ -

Professional Development

10 Qs

Guess the Event

Guess the Event

Professional Development

10 Qs

Svensqa -istqb-3

Svensqa -istqb-3

Professional Development

10 Qs

Estimating Techniques - Assignment

Estimating Techniques - Assignment

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Afghanistan Center

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Herat province, the project manager estimates the duration of building a new clinic by comparing it to a similar facility built last year in a nearby province. This method is quick but less precise. Which estimating technique is being used?

Analogous Estimating

Bottom-Up Estimating

Parametric Estimating

Historical forecasting using layered performance metrics, scope mapping, and feature parity regression

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A construction project in Nangarhar province estimates wall painting time based on the formula: 1 hour per 10 square meters. The team multiplies this rate by the total surface area. Which technique is this an example of?

Parametric Estimating

Analogous Estimating

Expert Judgment

Rate-based estimation using cost-size integration, productivity benchmarks, and phase-level historical modeling

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kunduz province, the team creates estimates for each small activity, then adds them up to develop the full schedule. This method is detailed and often time-consuming. Which estimating technique is being applied?

Bottom-Up Estimating

Analogous Estimating

Three-Point Estimating

Deliverable aggregation through progressive elaboration of activity subcomponents and micro-phase task alignment

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Barcelona city in Spain, the team uses best-case, worst-case, and most likely scenarios to estimate the time needed to install a fiber optic network. They apply a formula to calculate a weighted average. Which technique are they using?

Three-Point Estimating

Expert Judgment

Bottom-Up Estimating

Scenario-weighted time prediction using layered sensitivity analysis and resource spread adjustment

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Logar province, the team consults a subject matter expert with 15 years of experience on similar infrastructure projects to help define realistic activity durations. The expert’s input is based on both data and personal experience. Which technique is being used here?

Expert Judgment

Analogous Estimating

Bottom-Up Estimating