Cost Final Quiz - Assignment

Cost Final Quiz - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

5. PMP - Cost

5. PMP - Cost

Professional Development

10 Qs

MATS Lesson 7 - Starter

MATS Lesson 7 - Starter

Professional Development

8 Qs

Project Cost Management Knowledge Area

Project Cost Management Knowledge Area

Professional Development

10 Qs

Project Management

Project Management

Professional Development

10 Qs

Practice Exam 2 Part 2

Practice Exam 2 Part 2

Professional Development

10 Qs

Finance Sharing

Finance Sharing

Professional Development

10 Qs

Quality VS Grade - Assignment

Quality VS Grade - Assignment

Professional Development

7 Qs

SG20_Test_S5_CH6 Schedule

SG20_Test_S5_CH6 Schedule

Professional Development

10 Qs

Cost Final Quiz - Assignment

Cost Final Quiz - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While reviewing early construction work in Logar province, the project manager determines how much work was planned to be done by this stage in terms of budget.Which term is being used?

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

Timeline-based progress allocation calculated from budget phasing and scope delivery modeling

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Samangan province, the finance team compares the value of completed work to the money actually spent so far. They discover that the project is costing more than planned. Which performance metric identifies this overrun?

Cost Variance (CV)

Cost Baseline

Schedule Variance (SV)

Performance discrepancy index between spend-to-date and planned performance conversion

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A manager in Bamyan province wants to forecast how much the total project is likely to cost in the end, based on current trends and performance. Which term reflects this total predicted cost?

Estimate at Completion (EAC)

Budget at Completion (BAC)

Variance at Completion (VAC)

Forecast model using baseline deviation, burn rate, and corrective path analysis

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kabul, the project sponsor asks, “What’s the total authorized budget for this entire project?” Which cost management term best fits this request?

Budget at Completion (BAC)

Estimate to Complete (ETC)

Cost Baseline

Total allocation plan derived from approved work packages, contingency models, and spending thresholds

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A software project in Delhi, India, has a CPI of 0.85 and SPI of 0.90. The project manager needs to determine if the team is delivering value efficiently and staying on budget. Which metric should they focus on?

Cost Performance Index (CPI)

Schedule Variance (SV)

Estimate at Completion (EAC)

Efficiency ratio involving earned output velocity, task fulfillment pacing, and financial alignment