1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why must no person install a meter unless the installation is so placed as to ensure there is no risk of damage to it from electrical apparatus?

To prevent theft

To ensure the meter is visible

To avoid risk of electrical damage and ensure safety

To make maintenance easier

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to Regulation 12(4), where should a meter be installed?

In a hidden location

In a readily accessible position for inspection and maintenance

In the attic

In a locked room

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must be done immediately after installing a meter and associated gas fittings?

Paint the meter

Adequately test and examine to verify gas tightness and compliance with regulations

Leave it for 24 hours before use

Cover it with insulation

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a requirement under Regulation 14(2) for supplying gas from a gas storage vessel to service pipework or gas fittings?

A regulator installed to control the nominal operating pressure

Adequate automatic means for preventing over-pressure

Adequate alternative automatic means for preventing over-pressure

Manual monitoring of gas pressure every hour

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why does Regulation 16(1) prohibit the installation of a prepayment meter as a primary meter where gas is passed on to a secondary meter(s)?

Because if the prepayment meter runs out, it would cut off gas supply to all consumers on the system, leading to a potential risk of gas escape.

Because prepayment meters are more expensive.

Because secondary meters are not compatible with prepayment meters.

Because it is difficult to read the meter.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Suppose a person modifies an existing gas system so that more than one primary meter is supplied from a service pipe. What must this person do according to the regulations?

Ensure a permanent notice is displayed indicating that more than one primary meter is provided with gas through that service pipe or pipework.

Remove all secondary meters.

Install a new gas appliance.

Notify all residents in writing.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to Regulation 16(3)(b), what must be ensured when removing a meter if there is no service valve as mentioned in sub-paragraph (a)(i)?

Ensure that the service pipe or service pipework is disconnected as near as is reasonably practicable to the main or storage vessel and that any part of the pipe or pipework which is not removed is sealed at both ends with the appropriate fitting.

Leave the service pipework open for inspection.

Only disconnect the meter and leave the pipework untouched.

Seal only one end of the pipework.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development