Lesson-3 Plan The Project

Lesson-3 Plan The Project

Professional Development

24 Qs

quiz-placeholder

Similar activities

Knowledge Test - SEP'21

Knowledge Test - SEP'21

Professional Development

20 Qs

The Art of Online Teaching

The Art of Online Teaching

Professional Development

20 Qs

PKP

PKP

Professional Development

20 Qs

COVID-19 IPC Quiz

COVID-19 IPC Quiz

Professional Development

20 Qs

WAE Mock NQT Mixed

WAE Mock NQT Mixed

Professional Development

20 Qs

IEI Awareness Quiz - IEI Salem Local Centre

IEI Awareness Quiz - IEI Salem Local Centre

10th Grade - Professional Development

20 Qs

Safety In The Kitchen

Safety In The Kitchen

Professional Development

20 Qs

Ethics - Corporate Social Responsibility

Ethics - Corporate Social Responsibility

Professional Development

20 Qs

Lesson-3 Plan The Project

Lesson-3 Plan The Project

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

sudiyuwono wowo

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

24 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is the best elicitation technique to use when your project team wants to facilitate a discussion with a certain set of users to get a better understanding on how they might use your project’s product?

Document analysis

Focus group

Benchmarking

Plurality

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project team is reviewing the requirements documentation that they are responsible for working on. Which project artifact can they reference to see the connection between the requirements and the business and project objectives?

Requirements traceability matrix

RACI chart

Project charter

Scope management plan

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An architectural firm has spent a great deal of time and effort creating the design and blueprints for the building. They had to purchase materials and hire consultants and have been working on this project for 6 months. They have submitted all the invoices for the money they have spent on the work, as well as an invoice for the fee of $90,000. What type of contract was this?

Time and materials

Cost-plus-incentive-fee (CPIF)

Fixed-Price Economic Price Adjustment (FP EPA)

Cost-reimbursable

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is included in activity cost estimates?

Supporting data or additional information needed to justify the cost estimates

Estimates on probably costs necessary to finish project work, including direct costs, labor, materials, equipment, facilities services, information technology, and contingency reserves

Estimates on probable costs necessary to finish project, work based on the responsible bids obtained from vendors

Estimates on probable costs necessary to finish the project work, including direct labor, materials, equipment, facilities, services, information technology, contingency reserves, and indirect costs

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the process to create a project budget?

Take the rough order of magnitude (ROM) and decompose it into the cost of work packages

Combine all individual activity cost estimates and contingencies and aggregate them for the entire project. Submit this to the sponsor, and modify it if necessary

Estimate costs necessary to finish project work, including direct costs, labor, materials, equipment, facilities, services, information technology, and contingency reserves

Create an S-curve with cost on the Y axis and time on the X axis

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is using a time-phased budget to measure the cost performance. What is that budget called?

Cost baseline

Cost estimate

Rough order of magnitude

Release budget

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager informs the project sponsor that the project management plan will continuously increase in the level of detail as the project moves forward. In project management, what is this process known as?

Life cycle

Progressive elaboration

Resource planning

Scope creep

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Professional Development