Search Header Logo

Project Management Quiz

Authored by Training Pusilkom

Other

Professional Development

Used 1+ times

Project Management Quiz
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?

Weighing system

Screening system

Inspection and audits

Independent estimate

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The project manager and team have decided to hire a contractor to complete building out the remaining section of the datacenter. They have the requirements listed in detail and would like to use a contract that would present the smallest amount of risk to the project. The project team members would like to purchase the materials themselves since there are very familiar with the work. What contract is best for this project?

Cost plus contractor fee

Cost plus project fee

Time and materials

Cost plus fixed fee

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The sponsor makes it clear that he does not want any of the team members to be overworked while working on a project. This means that no team member is allowed to work overtime. The sponsor is okay with the project being delayed due to this. What technique can the project manager best implement to ensure that no team member is overworked?

Lag

Resource leveling

Resource smoothing

Free float

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

A large development company has just initiated a project to build a 60-story building. The project will take approximately 3 years to complete with a cost of $550 million. The development company has started to facilitate funding for the project by asking private equity firms and banks. What tools does this best represent?

Financing

Funding limit reconciliation

Analogous estimates

Parametric estimates

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The project manager has been informed that the company's senior management would like a meeting about the status of the project. What should the project manager take to display the current schedule of the project?

Gantt chart

Milestone chart

WBS

Network diagram

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

A project manager is currently working with the team to complete the office redesign project when a sponsor tells him to finish it 2 weeks sooner than planned. The project manager will need 4 new people to join the team to complete the work by the new deadline. What technique is best described in this scenario?

Critical path method

Schedule variance

Fast tracking

Crashing

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

After the start of a project, the project manager learns that an expected governmental subsidy may NOT be available. How should the project manager address this issue?

Log the risk

Raise the project's risk level

Make up any project deficit using the contingency reserve

Make a change request

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?