1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not referenced in the project statement of work?

Strategic plan
Business case
Product scope description
Business need

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is running a data center installation project. He finds that his stakeholder is angry because he’s run over his budget because the staff turned out to be more expensive than planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much drive space as he needs. Which of the following constraints was not affected by this problem?

Cost
Resource
Time
Quality

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are managing a software project. Your team has been working for eight weeks, and so far the project is on track. The lead programmer comes to you with a problem: there is a work package that is causing trouble. Nobody seems to know who is responsible for it, the accounting department does not know what cost center to bill it against, and it’s not even clear exactly what work should be performed. Which of the following would BEST help this situation?

Alternatives analysis
WBS dictionary
Scope validation
Scope Management plan

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following will be true about the value of the CPI at the end of any project?

It would be positive
Cannot be determined
It would be zero
It would be negative

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project Charter is an input in the following process, EXCEPT?

Define Scope
Scope Plan Management
Create WBS
Collect Requirement

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


This case study focuses on Earned Value Management (EVM), a project management technique that allows for the measurement of project performance and progress in terms of cost and schedule. The scenario describes the purchase and installation of a new web server with an initial planned cost and timeline, but both the timeline and budget exceeded the plan. Here's a breakdown: Planned Costs: Rp 100 million for technicians, hardware, and software, with a planned duration of 1 week. Actual Results: The installation took 2 weeks, and the total cost increased to Rp 200 million (Rp 150 million spent in the first week, and the remaining Rp 50 million in the second week). Progress: By the end of the first week, only 50% of the work had been completed


What are the Planned and Earned Values at the end of Week 1?

PV = Rp 100 million, EV = Rp 50 million
PV = Rp 50 million, EV = Rp 50 million
PV = Rp 50 million, EV = Rp 100 million
PV = Rp 100 million, EV = Rp 100 million

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

These questions are related to network diagrams in project management and the analysis of activity paths within a project. The table below illustrates the activities in the project along with their durations and dependencies, which determine how each activity relies on the completion of its predecessors.


When can activity G start?

After 9 days
After 11 days
After 10 days
After 5 days

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?