PM - Advanced Variance

Authored by pfc acca

Other

1st Grade

Used 4+ times

PM - Advanced Variance
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 2 pts

Which of the following statements is/are true regarding the material mix variance?

(1) A favourable total mix variance would suggest that a higher proportion of a cheaper

material is being used instead of a more expensive one.

(2) A favourable total mix variance will usually result in a favourable material yield

variance.

(1) only

Both (1) and (2)

(2) only

Neither (l) nor (2)

2.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

Which of the following concerning a labour planning variance is true?

A labour planning variance will always be adverse if actual labour rates increase

A labour planning variance will be caused by a manager changing the labour mix

during the year

A labour planning variance will be caused by an unexpected government policy to

increase labour rates

A labour planning variance will always lead to a variable overhead planning variance

3.

MULTIPLE CHOICE QUESTION

45 sec • 2 pts

Which of the following statements is/are true regarding the materials yield variance?

(1) An adverse total yield variance would suggest that less output has been achieved for

a given input, i.e. that the total input in volume is more than expected for the output

achieved.

(2) A favourable total mix variance will usually result in an adverse material yield variance.

(1) only

Both (1) and (2)

(2) only

Neither (1) nor (2)

4.

MULTIPLE CHOICE QUESTION

2 mins • 2 pts

A business advisor had planned to use 3 hours of labour on 700 client services in June.

Labour is paid $40 per hour.

In June there were actually 900 services provided. Total labour hours were 3,240 and the

actual labour rate was $42 per hour.

The advisor has since discovered that, due to a change in legislation that meant extra client

responsibilities, the budget should have provided for 3 h hours of labour per service.

What is the adverse planning labour efficiency variance for June (to the nearest $000)?

$18,000

$15,000

$10,000

$25,000

5.

MULTIPLE CHOICE QUESTION

2 mins • 2 pts

Media Image

What was the materials yield variance for March?

$6,800 favourable

$6,800 adverse

$1,000 favourable

$1,000 adverse

6.

MULTIPLE CHOICE QUESTION

2 mins • 2 pts

An organisation has recorded a favourable labour rate planning variance for the year of

$40,000.

On investigation it has discovered that, whilst actual labour rates were $60 per hour, a

revised standard rate for labour should have been $70 per hour for the actual hours worked

of 20,000.

What was the original planned labour rate per hour for the year (to the nearest $)?

$83

$67

$72

$70

7.

MULTIPLE CHOICE QUESTION

2 mins • 2 pts

Media Image

What is the total material mix variance?

$1,984 adverse

$7,216 adverse

$9,200 adverse

$16,416 adverse

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?