Building Layout and Foundation Techniques

Building Layout and Foundation Techniques

Assessment

Interactive Video

Mathematics, Architecture, Design

9th - 12th Grade

Hard

Created by

Aiden Montgomery

FREE Resource

The video tutorial guides viewers through the process of setting out a building foundation. It begins with preparation, including gathering tools and locating benchmarks. The tutorial then explains how to establish building lines and corners using the 3-4-5 method for right angles. It covers positioning profile boards and transferring markings to the foundation. Finally, it emphasizes the importance of checking measurements and making necessary adjustments before starting bricklaying.

Read more

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be ensured about the tools and equipment before starting the building layout?

They are in good condition and readily available.

They are new and unused.

They are borrowed from a neighbor.

They are expensive and branded.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where is the temporary benchmark typically set in this building layout process?

At the basement level

At the roof level

At the ground level

At the damp-proof course (DPC) height

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the first corner of the building established?

By estimating the position visually

By transferring the corner mark from the curb onto the building line

By measuring diagonally across the site

By using a compass to draw a circle

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What method is used to ensure right angles when marking the building's sides?

The 1-2-3 method

The 3-4-5 method

The 2-3-6 method

The 5-12-13 method

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be checked after marking all four corners of the building?

The width of the doors

The distance between the front and rear corners

The color of the pegs

The height of the roof

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of setting up profile boards?

To determine the color of the walls

To measure the height of the building

To identify the outer and inner wall positions

To mark the position of the windows

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be transferred onto the profile boards?

The type of flooring

The color of the paint

The position of the face line of the outer brickwork

The height of the roof

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?