Which of the following is NOT an information gathering technique mentioned in the risk identification process?
PMI-RMP Certification Training - Risk Identification – Tools and Techniques

Interactive Video
•
Information Technology (IT), Architecture, Business
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
SWOT analysis
Brainstorming
Delphi technique
Interviewing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of using a checklist in risk identification?
To finalize project timelines
To standardize the identification of risks
To ensure all team members are present
To allocate resources efficiently
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Assumptions analysis is used to:
Develop project budgets
Allocate project resources
Create project timelines
Validate project assumptions
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which diagram is also known as the fishbone diagram?
SWOT diagram
Influence diagram
Ishikawa diagram
Flowchart
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
SWOT analysis focuses on identifying:
Only threats
Only opportunities
Both threats and opportunities
Neither threats nor opportunities
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the role of expert judgment in the risk identification process?
To finalize project budgets
To develop project timelines
To allocate resources
To provide input from experienced team members
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which document is a key output of the risk identification process?
Project charter
Timeline schedule
Risk register
Budget report
Similar Resources on Quizizz
6 questions
PMI-RMP Certification Training - Perform Quantitative Risk Analysis – Tools and Techniques

Interactive video
•
University
6 questions
PMI-RMP Certification Training - Perform Qualitative Risk Analysis Process – Tools and Techniques

Interactive video
•
University
6 questions
PMI-RMP Certification Training - Perform Qualitative Risk Analysis Process – Tools and Techniques

Interactive video
•
University
6 questions
PMI-RMP Certification Training - Assumption and Constraint Analysis, SWOT Analysis and Checklist Analysis

Interactive video
•
University
8 questions
PMP Certification Training - Identify Risk

Interactive video
•
University
6 questions
PMI-RMP Certification Training - Critical Success Factor and Project Risk Ranking

Interactive video
•
University
6 questions
PMI-RMP Certification Training - Case Study 2

Interactive video
•
University
6 questions
PMI-RMP Certification Training - Key Takeaways - Perform Qualitative Risk Analysis

Interactive video
•
University
Popular Resources on Quizizz
10 questions
Chains by Laurie Halse Anderson Chapters 1-3 Quiz

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
15 questions
Character Analysis

Quiz
•
4th Grade
12 questions
Multiplying Fractions

Quiz
•
6th Grade
30 questions
Biology Regents Review #1

Quiz
•
9th Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
50 questions
Biology Regents Review: Structure & Function

Quiz
•
9th - 12th Grade
Discover more resources for Information Technology (IT)
10 questions
Identifying equations

Quiz
•
KG - University
16 questions
Chapter 8 - Getting Along with your Supervisor

Quiz
•
3rd Grade - Professio...
6 questions
Railroad Operations and Classifications Quiz

Quiz
•
University
71 questions
Logos

Quiz
•
3rd Grade - University
8 questions
Mali - Geography

Quiz
•
University