The deepest oil platform is Perdido. What is the type of the platform?
Fixed Platform
Tension Leg
Compliant Tower
Spar
New/open area, undeveloped oil and gas field. What is the term used to represent this field?
Yellowfield
Greenfield
Brownfield
Newfield
3 classes of Dynamic Positioning (DP) system. What actually differentiate class of the DP system?
Software
Redundancy
Hardware
Compartment
What is the typical method of Jacket Installation?
Hoisting
Sidelift
Driving
Launching
What is the highest crane capacity that Sapura Energy have?
3000 MT
2500 MT
3500 MT
4000 MT
Which of the following is not part of Installation Marine Spread
Fast Crew Boat
Supply Vessel
Anchor Handling Tug (AHT)
Slow Crew Boat
Which of the followings is not standards use in offshore installation works/study?
PTS
API
IBC
DNVGL
ROV is a short form for?
Remotely Offshore Vehicle
Remotely Operating Vehicle
Resistance Offshore Vehicle
Resistance Operating Vehicle
Which of the below is NOT the typical crew transfer method at offshore?
Personnel Basket Transfer
Boatlanding Transfer
Chopper Transfer
ILT Transfer