WorksheetsPre-Test Procurement Management
Total questions: 20
Worksheet time: 20mins
In order to procure required materials for a project, your team prepares documents that will be used to solicit information, quotations, and proposals from prospective sellers. The documents are structured to facilitate an accurate and complete response from each prospective seller and to facilitate the evaluation of the responses.
What type of documents is your team creating?
Vendor documents
Source selection criteria
Bid documents
Test and evaluation documents
Which of the following is an input to the Plan Procurement Management process?
Procurement management plan
Procurement strategy
Project charter
Stakeholder management strategy
You have completed a nine-month project, and you are in the closing stage. The project completed on time and under budget and everyone in you department has congratulated you on your achievement. The vice president of your company heard about the success of your project and wants a summary overview of project performance so that he can talk about your success at the next board meeting.
What should you provide to him?
Lessons learned repository
Project closure documents
Final lessons learned register
Final report
Two qualified vendors have been identified for a project. The requesting organization is capable of performing the work, but it was deemed less cost-effective to do so. During vendor selection, the project manager learns that one vendor already works with a competitor and are restricted by an exclusivity clause, The other vendor is not available during the required time frame.
What might the project manager have done differently to avoid this situation?
Include the evaluation method in the procurement documents
Obtained an independent cost estimate
Tailored the way the procurement processes were applied
Conducted a make-or-buy analysis
Where would you look to find what activities should be performed to close out contracts on your project?
Enterprise environmental factors
Resource management plan
Project management plan
Procurement documentation
Services are still being billed to the project even though the project manager believes no additional services are required or requested.
What is the best course of action for the project manager to take?
Confirm that no more services are needed and the procurement agreements are closed
Close all agreements with all service providers engaged with the project
Forward the service bills to the project management office for further review and approval
Continue paying the bills until the project is formally closed to avoid claims
You are leading a project with some of the deliverables outsourced to a vendor. You have been working closely with your procurement administrator to ensure hat all claims, invoices, and final payments have bee finalized with the vendor. Terms and conditions of the contract have been met, and all deliverables have been accepted.
What should you do next?
Notify the vendor that the contract has been completed
Finalize all activities for the project and release the project team
Conduct the final inspection of the vendor’s deliverables
Carry out a structured review of the procurement process
A project to design and develop a new prototype medical device will require several vendors to develop the subcomponents. As you review the responses to the RFP, you realize that all the vendors plan to re-use your competitors’ designs. This “re-use” is unacceptable for your company.
What is your best course of action?
Select a vendor based on the source selection criteria as specified by the approved project management plan
Add the intellectual property clause to the requirements documentation and ask the vendors to resubmit their proposals
Select a vendor based on the resource selection criteria and then add the intellectual property clause to the contract
Notify the legal department about the breach of contract and initiate alternative dispute resolution to settle the conflict
Services per the contract agreement with the vendor were delivered and signed off by the project manager.
What else must the project manager do?
Conduct a procurement audit
Close the procurement documents
Verify vendor scope
: Notify customer on services received
Per organizational policy, any commodities purchased for a project must be either the least cost option available or a sole source.
Which project process and tool and technique does this most impact?
Source selection analysis in Plan Procurement Management
Data representation in Identify Stakeholders
Pre-assignment in Acquire Resources
Accepted deliverables in Validate Scope
You are managing a project that is nearing its end and planning to settle all pending claims with the vendors. In one case, you are not satisfied with the delivery of their final product. All conversations with the vendor have been ended in an impasse.
What should you do in this situation?
Pay the vendor as some products were delivered
Take the vendor to court
Discontinue further meetings with the vendor and hold back payment
Identify some form of alternative dispute resolution
The project manager is in discussions with vendors about their bids that came in higher than expected. Additionally, according to the vendors’ responses, none of them will be able to deliver by the deadline requested. The project manager talks to the sponsor and other key project stakeholders to see if additional funds are needed to cover the extra costs and deliver on schedule.
Which process is the project manager performing?
Control Costs
Control Schedule
Acquire Resources
Conduct Procurements
Which element of the project management plan is NOT typically updated as an output of the Conduct Procurements process?
Communications management plan
Change management plan
Scope baseline
Procurement management plan
A vendor on a time and materials (T&M) contract to deliver corn for testing a new ethanol production facility is able to acquire the contracted materials at a dramatically lower price than expected due to a crash in the commodities market. The corn represents the single biggest expense for the project.
What is the best course of action?
Allow the project to proceed significantly under budget
Submit a change request to update the cost baseline
Split the cost savings with the vendor
Update the work breakdown structure (WBS)
A domestic vendor that is supplying the most critical component for a project you are leading is acquired by a major foreign conglomerate. The conglomerate has a history of replacing the executive team in the companies they acquire with new people from their corporate office. The only change that affects your project is that invoices are now payable to the conglomerate’s corporate office.
Which of the following project artifacts will you least likely need to update?
Communications management plan
Schedule baseline
Procurement management plan
Risk register
For a project, strict quality specifications must be followed, and all project team members were required to read and sign off on the quality management plan, acknowledging complete understanding of the specifications. The project manager suspects that one or more of the project’s primary material vendors is not supplying parts that meet project quality specifications.
What should the project manager do first?
Tell the vendor to replace the parts
Conduct a procurement performance review
Discuss the issue with the sponsor
Terminate the contract with the vendor
A project manager needs to secure a vendor to supply the avionics for a new line of small aircraft. There are only two vendors that are capable of meeting the requirements based on the procurement statement of work, and only one of the vendors has responded to a request for proposal (RFP). The project manager needs to evaluate the vendor’s proposal.
Which procurement document would provide a reasonableness check against the proposal submitted by the vendor?
Bid documents
Proxy estimates
Independent cost estimates
Bidder conference
During your project, you had contracted with an electrician to help with the electrical work for constructing an office building. You have completed your project ahead of schedule and under budget. You want to close out this procurement. However, you are unsure where you can find the requirements for the formal procurement closure.
What should you do?
Review the procurement statement of work
Consult with the project sponsor
Review the procurement agreement
Review closing documents
Your procurement manager has asked you to compare the current schedule and cost performance of the installations against what was promised in the agreement with the vendor.
What is the comparative process the procurement manager has asked for called?
A performance review
A procurement statement of work (SOW)
A procurement improvement plan
An audit
You are in the planning stage of a large project, which will require contracts with various vendors and suppliers to produce the project’s deliverables. With the procurement management plan and make-or-buy analysis complete, you are about to begin the development of a document that will outline the procurement strategy for the project.
Which of the following are you least likely to include in this document?
Procurement delivery methods
Type of agreements
Responsibilities of stakeholders
Procurement phases