PMP Question 100

Total questions: 100

Worksheet time: 2hrs 40mins

Name
Class
Date
1.

During a routine analysis of the project's reserves, the project manager realizes that some project costs have been saved due to the project taking advantage of an unexpected opportunity to outsource several activities.

What should the project manager do with these saved costs?

a)

A Record them as actual costs (AC)

b)

B Add them to the contingency reserves

c)

C Reduce them from the budget at completion

d)

D Credit them to the procurement department

2.

You are leading a software development project for an important client. For this project, you have elected to use a change-driven life cycle. Currently, you are about to lead an iteration planning meeting with the product owner and the development team.

What should you first accomplish at the start of the iteration?

a)

A With the project scope determined during initial project planning, the scope must be controlled to prevent scope creep

b)

B Disregard the fixed requirements and focus on those elements that are still evolving to determine the scope of the iteration

c)

C Define and approve the detailed scope of the iteration

d)

D Review and record lessons learned to correct processes and improve the performance of the upcoming iteration

3.

You have replaced a project manager midway through project execution. You discover that although financial project reports that include CPI and SPI are prepared weekly, the financial database repository has never been updated.

Which tailoring consideration did your predecessor most likely miss earlier in the project?

a)

A Project complexity

b)

B Knowledge management

c)

C Cost management plan

d)

D Earned value management

4.

During project execution, scheduling challenges have been experienced due to inclement weather that has resulted in multiple schedule variances. The project manager has noticed that a particular vendor is very flexible in scheduling their work. The project manager has found that the flexibility to adjust leads and lags is a particularly effective method for controlling the project schedule.


What should be done with this information?

a)

A Updated in the lessons learned repository

b)

B Noted in the schedule variance management plan

c)

C Documented in the lessons learned register

d)

D Included in the schedule baseline

5.

During product testing, a project team has discovered that some components did not meet government regulations established for the industry. Following the approved change request to repair the defects, the components have been fixed, and the team is ready to test the product again.

What documents should the team refer to while re-testing the product?

a)

A Verified deliverables

b)

B Resource requirements

c)

C Approved change requests

d)

D Quality improvement methods

6.

A project manager is having difficulty getting project team members to meet their weekly performance targets. The project manager has provided team training and team-building activities, but so far these and other efforts have been unsuccessful. The project manager would like to use a reward system to incentivize team members to meet their performance goals.

Which of the following strategies would be best?

a)

A Give all team members a raise to help motivate them

b)

B Give rewards to team members who meet their performance goals at the end of the project

c)

C Hold a contest where team members can compete for prizes

d)

D Consult the resource management plan

7.

You are leading a project to design a car with new self-driving technology. During project planning, existing government regulations regarding the new technology were virtually non-existent. You identified this ambiguity risk during project planning and developed a risk response. Now, with the car ready for production, new regulations have been enacted. The new regulations are so complicated that you have trouble understanding them and their implications for the project.

What should you do next?

a)

A Seek the opinion of a recognized expert to validate or modify the risk response

b)

B Terminate the project since the new technology does not meet the new regulations

c)

C Submit a change request to alter the scope baseline to accommodate the new regulations

d)

D Proceed with the project and implemented the risk response as originally planned

8.

A project manager is holding a meeting with relevant stakeholders to perform a benefits analysis for a project that has been selected by the company. The project is codenamed Project Tiger and has a net present value of $3,000,000. One of the meeting participants asks about Project Panther, which was estimated to have a net present value of $2,500,000. The project manager explains that Project Panther was rejected because the company did not have the resources to support both projects.

What else might the project manager state in this scenario?

a)

A The $2,500,000 is the opportunity cost

b)

B The $2,500,000 is considered sunk cost

c)

C The $500,000 is the opportunity cost

d)

D The $3,000,000 is considered sunk cost

9.

A project manager is holding a meeting with relevant stakeholders to perform a benefits analysis for a project that has been selected by the company. The project is codenamed Project Tiger and has a net present value of $3,000,000. One of the meeting participants asks about Project Panther, which was estimated to have a net present value of $2,500,000. The project manager explains that Project Panther was rejected because the company did not have the resources to support both projects.

What else might the project manager state in this scenario?

a)

A The $2,500,000 is the opportunity cost

b)

B The $2,500,000 is considered sunk cost

c)

C The $500,000 is the opportunity cost

d)

D The $3,000,000 is considered sunk cost

10.

A project is divided into phases. Each phase consists of tasks involving design, development, testing, and integration. You have developed a project charter, and the project sponsor has just signed and approved the charter.

The purpose of this document includes all of the following, except:

a)

A To provide a direct link between the project and the company's strategic objectives

b)

B To provide a formal record of the project

c)

C To show organizational commitment to the project

d)

D To authorize functional management responsibilities to the project manager

11.

Which of the following best describes the key benefit of the Plan Stakeholder Engagement process?

a)

A Enables efficient communication between the project team and stakeholders

b)

B Increases probability of meeting the quality objectives established for the project

c)

C Provides an actionable plan to interact effectively with project stakeholders

d)

D Describes the product, service, or result boundaries and acceptance criteria

12.

The project team is reviewing the project charter and project management plan to develop a detailed description of the project and the product.

What is another document the team should review to complete their work?

a)

A Work breakdown structure

b)

B Risk register

c)

C Quality control measurements

d)

D Change log

13.

As part of product testing, a team member wants to verify compliance of the product with pre-defined specifications.

What should the team member use to compare her test results?

a)

A Affinity diagram

b)

B Quality metrics

c)

C Activity list

d)

D Quality audit

14.

A project to build a new high-end subdivision has been plagued with quality problems. Customers are arguing about what was actually specified to be built. The last house has been built, and the fixes to five more houses have been completed. The project manager desperately wants to close the project and move on.

What does the project manager need to review to ensure proper closure of the project?

a)

A All components of the project management plan

b)

B The quality management plan to ensure it was followed for these last few houses

c)

C The requirements management plan to ensure all the requirements are met

d)

D The performance measurements baseline to ensure determine how the project performed

15.

A change control board (CCB) has been established for the project you are leading. During project execution, the client contacts you to request a change to a project deliverable which can be accommodated with existing project resources and will not increase cost.

What should you do next?

a)

A Ask the project sponsor to approve the implementation of the change

b)

B Request the change control board (CCB) to approve the change

c)

C Submit the change request and evaluate it against other project constraints

d)

D Implement the change as requested by the customer

16.

A project manager and team are in the process of finalizing all project activities. They have obtained final acceptance and transferred ownership of deliverables, obtained administrative closure, collated lessons learned, archived all project documents, and obtained feedback from relevant stakeholders. Finally, the project manager and team have been released and reassigned to other assignments.

Based on the information provided, what might have been forgotten?

a)

A Verifying that project deliverables conform to the quality management plan

b)

B Reviewing and assessing detailed project requirements

c)

C Preparing and sharing the final project report

d)

D Conducting benefit analysis with relevant stakeholders

17.

You have just taken over a project, which is in the process of project closure. The project has experienced numerous setbacks, which have caused cost and schedule overruns. You want to ensure that any mistakes that were made in the project are not repeated to ensure improved performance for future projects.

What is the best course of action in this situation?

a)

A Perform stakeholder analysis

b)

B Conduct reserve analysis

c)

C Perform document analysis

d)

D Conduct technical performance analysis

18.

The change control board (CCB) is evaluating a recently submitted change request. The project sponsor wants to deny the request. Another stakeholder is in favor of deferring the request until a later date. The project manager and other stakeholders feel it is best to approve the request. The project manager is unsure how to proceed since there is disagreement among the stakeholders.

What should the project manager do?

a)

A Defer the request until all of the stakeholders are in agreement

b)

B Deny the request as the project sponsor has the final say

c)

C Consult the project management plan

d)

D Approve the request as the project manager has authority to decide for the group

19.

A project has been broken down into four phases. The first phase is design, the second is coding, the third is testing, and the final phase is the deployment. The first two phases have already been completed. The project team has just completed all testing activities of the third phase and reports to the project manager that the deliverables have been verified. The project manager is pleased and wants to begin deployment as soon as possible.

What should the project manager do next?

a)

A Ensure the sponsor has signed the charter for the fourth phase

b)

B Begin the Close Project or Phase process of the testing phase

c)

C Obtain acceptance of the deliverables from the testing phase

d)

D Hold the fourth phase kick-off meeting with the project team

20.

You are leading a project to build a storage facility next to an estate managed by a homeowner association (HOA), who has been classified as an influential stakeholder. During project planning, the HOA has expressed their objection that the facility is an eyesore, so it has been agreed that large trees will be planted to obscure the view to the facility. The construction has begun, but some of the HOA members are still unhappy with the project.

What should you do now?

a)

A Proceed with the project as planned

b)

B Add the HOA to the stakeholder register

c)

C Remove the HOA from the stakeholder register

d)

D Communicate regularly with the HOA

21.

You have just taken over a project in execution from another manager. In your first week, you are unpleasantly surprised to receive emails from several stakeholders asking questions about the project objectives as well as their roles and responsibilities on the project. You are also concerned about what appears to be a lack of commitment to the project by the team.

What did the initial project manager most likely miss?

a)

A Conducting the project kick-off meeting

b)

B Creating a RACI chart

c)

C Identifying the key project stakeholders

d)

D Developing the team charter

22.

Due to a large number of team members working remotely and the time differences between them, you are having difficulty coordinating meetings with team members. This situation negatively impacts team cohesion.

Which of the following tools would be the most beneficial for you to use?

a)

A Interpersonal skills

b)

B Conflict management

c)

C Communication technology

d)

D Team performance assessments

23.

A project manager reviews surveys from participants of a recent project meeting. Based on the feedback provided, it is evident that attendees in the back of the meeting room had difficulty hearing the speakers and seeing the slide presentation. Some have suggested having the presenters use microphones as well as distributing hard copies of the presentation before the meeting, so all of the attendees can better follow along.

What should the project manager do next?

a)

A Update the lessons learned repository

b)

B Revise the stakeholder register

c)

C Reduce the number of participants invited to future meetings

d)

D Capture the information in the issue log

24.

Senior management is considering a project to replace the company's inventory tracking system, and the pre-project work is underway. At this point, the project needs assessment has just been completed.

What should be done next?

a)

A Selecting a new inventory tracking system

b)

B Acquiring project team members

c)

C Carrying out the project kick-off meeting

d)

D Identifying key project deliverables

25.

A system delivered by a vendor on your project does not perform as specified. Your boss has instructed the procurement department to withhold the payment. The vendor has filed a claim for non-payment.

What should you do first?

a)

A Attempt to negotiate a resolution with the vendor

b)

B Do nothing as the system is not fit for use

c)

C Resort to alternative dispute resolution (ADR)

d)

D Contact the legal department to file suit for damages

26.

You are working at a firm where your responsibilities include selecting the right programs or projects, prioritizing the work, and providing the needed resources. Your primary objective is to manage all of the various programs, projects, and operations together as a group to meet the firm's strategic business objectives.

Which of the following best describes the work you are performing?

a)

A Operations management

b)

B Project management

c)

C Program management

d)

D Portfolio management

27.

You have just finalized the project management plan. It must now be reviewed and approved by the relevant stakeholders.

What is the best way to present the project management plan to have it reviewed and approved?

a)

A Send an email with an electronic copy of the project management plan to the relevant stakeholders

b)

B Conduct a meeting with the relevant stakeholders

c)

C Review the project management plan with the project team during the next team meeting

d)

D The project manager approves the project management plan, so no further action is needed

28.

You are leading a large and complex project, which requires various vendors and suppliers to provide project deliverables. One of your vendors contacts you and states that they have just completed their contracted work and would like to know when they will receive final payment.

How might you respond to the vendor's question?

a)

A Once we have verified that you are on our prequalified seller list

b)

B After we provide you with formal written notice that the contract has been completed

c)

C After we have approved all of your deliverables

d)

D When we perform project closure, we will release final vendor payments

29.

On a project you are managing, you have been unable to obtain landlord approvals to install cable at various retail locations. You just learned about a project undertaken by your organization in the past that faced similar issues. If you had been aware of them during project planning, you could have taken proactive steps to avoid or mitigate the problems on your project.

What might have been done differently to incorporate the knowledge gained from the previous project into your project?

a)

A Development of more comprehensive risk response plans

b)

B Better communication between project managers within the company

c)

C Improved utilization of the organizational knowledge base

d)

D Utilization of a lessons learned register for your project

30.

During project execution, you discovered that some of the key stakeholders are not keeping up with project developments. The stakeholders indicate that most of the information on the weekly reports are irrelevant and they do not have time to read all of the content. As a result, these stakeholders have missed several key action items, thereby, putting the project behind schedule.

What is most likely the cause of this issue?

a)

A Emailing the report rather than allowing the stakeholders to pull the information at their convenience

b)

B Sharing the report using information radiators instead of social media

c)

C Sending the same report to all stakeholders

d)

D Withholding pertinent information from the report

31.

A project manager is leading a project, which has experienced greater than anticipated weather-related delays. To keep the project on schedule, the project manager will need to access the contingency reserves allocated for this risk.

What should the project manager do next?

a)

A Submit a change request to access the contingency reserves

b)

B Escalate the issue to the key project stakeholders

c)

C Access the contingency reserves as needed to meet the project objectives

d)

D Send a request to the project management office (PMO)

32.

On a project, work performance data is being regularly collected and shared with the project team.

Which of the following processes will use this data?

a)

A Develop Project Charter

b)

B Plan Quality Management

c)

C Monitor Stakeholder Engagement

d)

D Analyze Performance Data

33.

A project manager is near the end of a large and complex project, which required the services of several different vendors. Currently, the project manager is about to start the process of finalizing all activities for project closure.

What should the project manager do first?

a)

A Submit a change request to update the project management plan

b)

B Update all applicable project documents and mark them as final versions

c)

C Revise and finalize the business case and the project charter

d)

D Begin the alternative dispute resolution procedure with the vendors

34.

You are leading a project to develop a software application. The application is being built incrementally using a scrum framework. Due to low stakeholder engagement, you submit a change request to update the stakeholder engagement plan with an invitation for key project stakeholders to participate in sprint planning and retrospectives.

What tool or technique are you planning to use?

a)

A Expert judgment

b)

B Meetings

c)

C Communication skills

d)

D Stakeholder register

35.

You are about to hold a kick-off meeting to begin planning for a small project you have been assigned to manage. A stakeholder who has been out of the office for most of the project's initiation phase, asks you for more information about how the project will impact his department.

Which one of the following would be the most appropriate to provide the stakeholder?

a)

A The project scope statement

b)

B The approved project charter

c)

C The project management plan

d)

D The business case

36.

Midway through your project, you are informed by a member of the project staff of a growing problem with two primary team members. After learning of verbal encounters and the negative effect on the team, you decide immediate action is needed. You meet privately with the two team members involved and collaboratively agree on steps to eliminate the conflict. Follow-up meetings are scheduled to discuss the ongoing progress.

Based on the information provided, which of the listed actions should you take next?

a)

A Update the schedule baseline

b)

B Update organizational process assets

c)

C Update the issue log

d)

D Update the enterprise environmental factors

37.

In order to procure required materials for a project, your team prepares documents that will be used to solicit information, quotations, and proposals from prospective sellers. The documents are structured to facilitate an accurate and complete response from each prospective seller and to facilitate the evaluation of the responses.

What type of documents is your team creating?

a)

A Vendor documents

b)

B Source selection criteria

c)

C Bid documents

d)

D Test and evaluation documents

38.

A project manager discovers that due to schedule conflicts, some key stakeholders have not been attending a weekly conference call where important decisions are made. To address the issue, the project manager proposes to establish alternative communication methods.

Which of the following will likely be updated as a result of this proposal?

a)

A Quality management plan

b)

B Communications management plan

c)

C Work breakdown structure

d)

D Stakeholder engagement assessment matrix

39.

Preorders for the new product you are developing have significantly exceeded expectations, and current production will not meet demand. This situation presents the company with a significant threat and opportunity. You need to take action to mitigate the negative impact of the risk and enhance the opportunity. You know this risk was captured during the Identify Risks process but are unsure of the risk owner and the agreed-upon risk response.

What should you do next?

a)

A Review the project charter

b)

B Hire external contractors and crash the schedule

c)

C Review the risk register

d)

D Review the requirements traceability matrix

40.

A project manager is leading a research and development project and is currently performing the Close Project or Phase process. As part of this process, the project manager is preparing the final project report.

Which of the following is least likely to be included in the final report?

a)

A Summary level description of the project

b)

B Summary of the lessons learned during the project for use on future projects

c)

C Summary of risks or issues encountered on the project

d)

D Summary of how the final product achieved the business needs identified in the business plan

41.

A project manager is uncertain what resources are needed to complete the project. To help with the planning process, the project manager breaks down the resources using a data representation tool that displays the physical and human resources related by category and resource type.

Which answer choice best describes the tool that the project manager is using?

a)

A Work breakdown structure (WBS)

b)

B Physical breakdown structure (PBS)

c)

C Organizational breakdown structure (OBS)

d)

D Resource breakdown structure (RBS)

42.

A project has been initiated and is being planned. The project sponsor is anxious for the project to move into execution and suggests that the project manager not spend any more time on the development of the communications management plan.

How should the project manager respond to the sponsor to support the completion of the communications management plan?

a)

A The communications management plan is a required part of the project management plan.

b)

B The communications management plan is required by The Standard for Project Management.

c)

C The communications management plan assists with stakeholder engagement.

d)

D The communications management plan will improve quality.

43.

You recently started working part-time at a small roofing company. The owner hired you to manage the roofing team's activities while he attends to other endeavors. There is no other administrative staff, and you must consult the owner regarding any important project decision, including budget allocation.

Which of the following best describes your role?

a)

A Functional manager

b)

B Project manager

c)

C Project coordinator

d)

D Project sponsor

44.

A project manager has just completed the development of the project management plan and wants to determine who is responsible for approving it.

What is the best course of action for the project manager?

a)

A Check the organizational process assets

b)

B Research the relevant enterprise environmental factors

c)

C Ask the project sponsor what to do

d)

D The project management plan does not require a formal approval

45.

As part of project closure, the project manager archives all of the project documents and materials in accordance with the company's policies and procedures.

Which of the following is the least likely reason for this activity?

a)

A To comply with statutory requirements

b)

B For potential use in future projects

c)

C To improve the performance of the current project

d)

D To be available for any future audits

46.

One risk that had been identified and accounted for during the planning process of your construction project was delays caused by poor weather. However, the abysmal weather has exhausted the schedule reserves, and the project schedule is unattainable despite your best efforts. As a result, the project sponsor asks you to update the schedule baseline.

What should you do next?

a)

A Update the schedule baseline as per the sponsor's request

b)

B Submit a change request

c)

C Crash the schedule

d)

D Fast track the schedule

47.

Your project is behind schedule. To get the project back on track, you implemented the previously planned risk response of crashing the schedule. With the project back on schedule, you and your team perform a variance analysis to compare the planned risk response to the actual impact on the schedule and cost.

What have you and your team produced as the result of this analysis?

a)

A Work performance information

b)

B Risk register

c)

C Risk management plan

d)

D Risk abatement report

48.

You are leading a project to manufacture a new type of electric vehicle. The lessons learned repository indicates that past projects have had issues with paint scratches after the installation of the exterior trim. The engineering department has recommended the application of a vinyl film to the painted surfaces of the cars after leaving the paint booth.

The application of the vinyl film is an example of what?

a)

A Preventive action

b)

B Corrective action

c)

C Defect repair

d)

D Protective action

49.

You are leading a corporate restructuring project. During a meeting intended to build support for the project among key stakeholders, a gap is uncovered with regard to conducting monthly audits for regulatory compliance. Specifically, the project management plan does not address who will be responsible for conducting this activity in the new organizational structure. Apparently, this project requirement was missed during project planning.

What should be done next to resolve this issue?

a)

A Reevaluate the Collect Requirements process

b)

B Capture the information in the lessons learned register

c)

C Add a new risk to the risk register

d)

D Submit a change request

50.

You are creating a quality management plan. Some of the requirements were derived from the standards outlined in various government regulations.

What should you do to find an overview of the tests required to verify that those requirements have been met?

a)

A Review the requirements register

b)

B Read the requirements management plan

c)

C Conduct a review of the assumption log

d)

D Examine the requirements traceability matrix

51.

You are managing a medical research project, which requires the collection and freezing of blood samples. The stability of the blood samples depends on the freezer maintaining a constant temperature. You have decided to split the samples and place them in two separate freezers in case one of the freezers fails. You have also plugged both freezers into power outlets that will be supported by an emergency generator in case of a power outage.

Which risk response strategy have you applied?

a)

A Mitigate

b)

B Transfer

c)

C Escalate

d)

D Accept

52.

Your project has been plagued with numerous change requests.

What is the most likely reason?

a)

A Incomplete stakeholder register

b)

B Lack of a detailed procedure to close the project

c)

C Failure to implement risk responses

d)

D Change management plan did not authorize a change control board

53.

For your project, you are unsure if a part can be manufactured using the new material according to the ultra-precise thickness required.

What would be the best tool to determine if the production line is consistently producing parts with the required quality standards?

a)

A Ishikawa diagrams

b)

B Control charts

c)

C Flowcharts

d)

D Statistical sampling

54.

A project manager wants to take advantage of the corporate project management information system (PMIS) to ensure that stakeholders can easily retrieve the non-sensitive and non-confidential information. Following the communications management plan, the project manager needs to provide the stakeholders with the opportunity to form online communities.

What is the best course of action for the project manager to achieve this goal?

a)

A Reserve a meeting room where stakeholders can socialize

b)

B Invite stakeholders to attend daily standup meetings

c)

C Utilize audio and video conferencing, email, fax, and voicemail

d)

D Use social media communication management tools

55.

You and your project team hold a meet-and-greet with the key stakeholders from a distant country to help build rapport. Feedback after the meeting indicates that your project team felt the stakeholders were distant and aloof as they kept stepping back when engaged in conversation. Whereas, some of the stakeholders thought you and the project team were too pushy and did not respect their personal space.

What could have helped you to avoid these perceptions?

a)

A Better cultural awareness

b)

B Improved political awareness

c)

C Conducting the meeting virtually

d)

D Applying conflict management skills

56.

Project team members develop a document that describes values that are important to the team's success such as sharing best practices, listening to each other with an open mind, and communicating respectfully during meetings.

What would be the result of the team's effort?

a)

A Team management plan

b)

B Team charter

c)

C Resource management plan

d)

D Resource requirements

57.

You are reviewing a document that describes the project vision, mission, purpose, objectives, and success criteria; high-level requirements, risks, and assumptions; the list of key stakeholders, and the name of the assigned project manager.

What else should be specified in this document?

a)

A The business need and the cost-benefit analysis

b)

B Requirements for formal procurement closure

c)

C Development approach and project life cycle

d)

D Milestone schedule and key deliverables

58.

The latest iteration in the project went far better than the first iteration. Some claim it was the increased communication. Others credit the change in the social media strategy. While others feel it was due to the inclusion of a training course.

What should the project manager do to make the next iteration even more successful?

a)

A Include another training course in the next iteration

b)

B Update the lessons learned register with what worked well

c)

C Double the communications in the next iteration

d)

D Increase the usage of the social media tools in the next iteration

59.

Which of the following best describes the Manage Quality process?

a)

A Identifying quality requirements and standards for the project and its deliverables

b)

B Leading and performing the work defined in the project management plan

c)

C Monitoring and recording results of executing the quality management activities

d)

D Translating the quality management plan into executable quality activities

60.

As part of project initiation, the project manager reviews the business documents, creates the stakeholder register, and helps the sponsor with the development of the project charter.

What else should the project manager do before moving on to project planning?

a)

A Develop the stakeholder engagement plan

b)

B Conduct a benefit analysis with relevant stakeholders

c)

C Send bid documents to prospective sellers

d)

D Determine the project budget and develop the schedule

61.

As part of the routine activities to monitor and control the performance of your project, you determine that the project SPI is 0.8. In order to get the schedule back into alignment with the plan, you authorize the overtime pay for the project team.

Which of the following best describes the tool or technique you used to align the schedule?

a)

A Scheduling tool

b)

B Schedule compression

c)

C Leads and lags

d)

D Fast tracking

62.

A project team member has been tasked to develop the change management plan. The team member is looking for the approved template of the change management plan.

What is the best course of action for the team member?

a)

A Check the organizational process assets

b)

B Use a change management plan from the previous project

c)

C Research the lessons learned repository

d)

D Find a suitable template from an Internet search

63.

A project manager is in the process of identifying quality requirements and reviews the lessons learned from a similar past project. The other project ran significantly over budget due to the high cost of nonconformance resulting from inadequate spending on the cost of conformance. The project manager does not want his project to suffer the same fate as the failed project.


Which data analysis technique should the project manager use in this situation?

a)

A Cost of quality

b)

B Benchmarking

c)

C Testing and inspection planning

d)

D Risk register

64.

You are planning risk management activities for a small project you are leading. The project team is having trouble assigning cost and schedule impacts to identified risks due to a lack of high-quality numeric data.

What is your best course of action?

a)

A Make up numeric data and evaluate on a quantitative basis

b)

B Release the project team and terminate the project

c)

C Proceed directly to the Plan Risk Responses process

d)

D Request the numeric data from the project sponsor

65.

During project planning, a risk was identified that the vendor contracted to supply materials for the project may not be able to meet the contractual requirements. The response to this risk was to contract with a secondary vendor at a higher cost, and contingency reserves were set aside for this risk. Eventually, during project execution, the risk was realized, and the secondary vendor has been contracted to provide the remainder of the needed material.

What should the project manager do first?

a)

A Perform the Conduct Procurements process

b)

B Update the risk register

c)

C Implement the agreed-upon risk response

d)

D Submit a change request to update the cost baseline

66.

To hire independent contractors for the project team, the project manager follows the resource management plan and advertises the opportunity on social media. The response is overwhelming. After narrowing down the list of applicants to those qualified for the project work, the project manager has a much larger than anticipated candidate pool.

What should the project manager do next?

a)

A Apply the source selection criteria to the candidate pool

b)

B Submit a change request to update the resource management plan

c)

C Update the lessons learned repository

d)

D Use multicriteria decision analysis to select the team members

67.

To create a schedule model for project execution and monitoring and controlling, you analyze activity sequences, durations, resource requirements, and schedule constraints.


What would be the most likely outcome of the process you are performing?

a)

A Schedule management plan

b)

B Monte Carlo probability distribution

c)

C Detailed Gantt bar chart

d)

D Schedule forecasts

68.

You have started gathering documents you need to implement a planned response to a realized risk. You need a document that will provide summary information on identified risks, as well as an assessment of the current project risk exposure.

What is the input document you need?

a)

A Lessons learned register

b)

B Project charter

c)

C Assumption log

d)

D Risk report

69.

During an initial project planning meeting, the project team decides to save a portion of cost estimates in the work package to offset the potential risk of advances in technology, which would make their current equipment obsolete.

What is the best course of action for the project manager?

a)

A Create a management reserve

b)

B Submit a change request

c)

C Create a contingency reserve

d)

D Do nothing as the risk has not yet realized

70.

The stakeholder engagement plan has just been approved.

Which of the following is least likely to trigger an update to this plan?

a)

A The start of a new phase of the project

b)

B Changes to the organizational structure

c)

C The closure of a project or phase

d)

D Changes in communications strategies

71.

While creating the project charter, you review the business case and learn that, unlike previous projects, this project will source non-sustainable wood for the product, which substantially reduces project cost. Your company has had some financial difficulties lately, but you know it has high environmental standards and always marketed and prided itself on producing goods that are 'green'.

What is your best course of action?

a)

A Update the business case to specify sustainable wood to be used in the project

b)

B Continue to create the project charter according to the business case

c)

C Hold on the development of the project charter and ask the sponsor for advice

d)

D Specify in the project charter the use of a sustainable wood source

72.

A project to renovate a city park affects the residents of the neighboring condominium complex. A website is being used to keep the residents informed of the progress of the renovation.

Which communication method is being used in this scenario to share information with the residents?

a)

A Push communication

b)

B Pull communication

c)

C Interactive communication

d)

D A communication model

73.

A project manager is executing the quality management plan of a project to develop a prototype medical device. Given the nature of the project, the quality standards are very stringent. With no known cause, it becomes apparent that the product quality does not meet project requirements.

What is the best course of action for the project manager to take in this situation?

a)

A Direct the project team to improve the quality of their work

b)

B Ask the project sponsor what to do

c)

C Create an affinity diagram

d)

D Develop an Ishikawa diagram

74.

A project is underway to construct a wind farm in an area with no communication infrastructure. The plan is to monitor progress and coordinate the scheduling of the project activities using project management software and provide daily status updates to the project sponsor at the home office. Two project teams will work and reside onsite in rotating seven-day tours.

Which of the following is the most likely challenge the teams will face while controlling the schedule?

a)

A Stability of requirements

b)

B Technology support

c)

C Human resource availability

d)

D Project importance

75.

After the project charter has been completed and approved, the project manager immediately begins the process of developing the project management plan.

What might the project manager have forgotten to create?

a)

A Risk log

b)

B Assumption log

c)

C Issue log

d)

D Change log

76.

A project manager is leading a project to restore numerous historical artifacts, which were damaged in a fire at a museum. Due to the value of some of the art, security will be paramount for this project. The project manager needs to increase the engagement level of key stakeholders and plans to bring the stakeholders onsite to review the progress.

Before bringing the stakeholders onsite, what should the project manager do first?

a)

A Ensure the stakeholders understand the ground rules established in the team charter

b)

B Check the company's organizational process assets

c)

C Ask permission from the project sponsor

d)

D Schedule extra security personnel for the onsite review

77.

You are the project manager who is in the process of preparing the project planning documents. As you gather data, you want to be as thorough as possible given the vast scope of the project. Therefore, you want to use a standardized list of items to be considered during this process.

What should you do to find this information?

a)

A Check the lessons learned repository

b)

B Consult the project management plan

c)

C Check the organizational process assets

d)

D Review the scope baseline

78.

You are taking over a wastewater treatment project from an experienced colleague who is retiring. During the handoff, the retiring project manager suggests that ten large valves required for the project be ordered immediately since they are long lead items from the vendor. This information is recorded in the project assumption log. A delay in the valves delivery could delay the project. The valves are very costly, and you are not sure about spending so much money this so early in the project which is still in planning.

What is the best course of action?

a)

A Order the valves and make sure they are categorized correctly as critical items in the project resource management plan.

b)

B Request the project sponsor to prevent the retiring project manager from leaving the company before completing the project.

c)

C Negotiate for five valves since it will only expend half of the budget for these items and will not raise unwanted attention.

d)

D Ignore the retiring project manager's suggestion since in the global marketplace, any item can be procured at any time on demand.

79.

During the development of the stakeholder engagement plan, the project manager realizes that a key stakeholder is resistant to the project. Without the support of this stakeholder, the project may fail.

What is the best course of action for the project manager to identify the reason for the stakeholder being resistant?

a)

A Escalate to the project sponsor

b)

B Update the stakeholder register

c)

C Use the mind mapping technique

d)

D Utilize an Ishikawa diagram

80.

Early in project planning, your team identified increases in the cost of raw materials as a project risk. Due to a recent natural disaster, raw material costs are expected to quadruple. You had originally set aside a contingency reserve to account for some cost variance. However, after analyzing current prices, you are uncertain if that contingency reserve will be sufficient.


What technique should you use to evaluate this uncertainty?

a)

A Plan risk management

b)

B Risk reassessment

c)

C Reserve analysis

d)

D Risk audit

81.

You have been hired by a start-up company that is about to undertake its first software development project. You are in the process to determine what resources will be required to carry out the project work.


What tools or techniques would be most useful for you to complete this process?

a)

A Resource leveling

b)

B Resource histogram

c)

C Analogous estimating

d)

D Bottom-up estimating

82.

You are leading a project to develop a more energy efficient commercial refrigeration system. During testing of the prototype, a defective component is discovered within the compressor.

With the approval obtained to repair the defective part, what should be done next?

a)

A Perform the Integrated Change Control Process

b)

B Submit a change request

c)

C Repair the defect

d)

D Replace the compressor

83.

A project to construct a new cruise ship is in the execution stage when a small crack is discovered in the mount of the engine. The decision is made to apply stop-drilling and then weld the crack. After the welding is complete, the part is inspected, painted, and returned to service.

Which of the following best describes the action taken in this scenario?

a)

A A defect repair was performed.

b)

B A preventive action has been undertaken.

c)

C A corrective action has been taken.

d)

D A proactive measure has been completed

84.

A buyer has subcontracted a critical component of their product and wants to ensure strict oversight over its development and manufacturing. To address this need, it has been suggested to carry out periodic performance reviews.

During which project management process will the buyer conduct these reviews?

a)

A Conduct Procurements

b)

B Control Procurements

c)

C Control Scope

d)

D Plan Procurement Management

85.

The project you are managing has launched its product, and you have begun working through the administrative closure of the project. Many risks were identified throughout the project, and you want to ensure that now, as you are closing the project, there are no open risks and that the overall project risk is within the defined level.

What is the best document to review for this information?

a)

A The risk report

b)

B The risk management plan

c)

C The issue log

d)

D The risk repository

86.

The following Gantt chart displays the current schedule status for a construction project. At this point in the project, the first two activities, Select Site and Negotiate Lease, should have been completed along with 50% of the work associated with the third activity, Perform Civil Works. However, only the first two activities have been completed, and no work has been done on the third activity. The method used to determine the earned value is based on percent complete.

What is the project's current SPI and what does this mean for the project?

a)

A The project is currently behind schedule with an SPI of 0.5

b)

B The project is currently behind schedule with an SPI of 2.0

c)

C The project is on schedule with an SPI of 1.0 due to the fast-tracking of activities

d)

D The project is currently behind schedule with an SPI of -$10,000

87.

You are leading a project to design a new and innovative system based on newly developed technology. In past projects, using a traditional waterfall project management approach, you have encountered issues with scope creep. However, given the nature of the current project, you have decided to use an agile approach.

As it relates to project scope, how will this project differ from your past projects?

a)

A The project scope will evolve during the project

b)

B During initial project planning, a more detailed work breakdown structure will be created

c)

C Scope creep will be avoided with a strict change management system

d)

D The project scope will be better understood at the beginning of the project

88.

As a project manager, you are in the initiation stage of a new project. You are currently preparing for a meeting to conduct a benefit analysis with relevant stakeholders to validate project alignment with organizational goals and expected business value.

What should the project manager do to prepare for the meeting?

a)

A Review the project management plan

b)

B Examine the project business documents

c)

C Read the stakeholder engagement plan

d)

D Study the project alignment plan

89.

To comply with the customer's contract, the project must use a certified agile practitioner to lead and coach the project team. However, the only certified agile practitioner employed by the company was just assigned to another project. The project manager must now hire an independent contractor to serve as the agile coach, which delays the start of project execution.

Which of the following may have helped to avoid the delay in executing the project?

a)

A Using different verbiage in the resource management plan to remove the requirement for an agile coach

b)

B Documenting the potential unavailability of the agile coach in the project assumption log

c)

C Securing the internal agile certified practitioner with a pre-assignment when this requirement was first identified.

d)

D Assigning a different team member from the company to serve as the agile coach

90.

A project manager is performing quality assurance for a project whose quality standards are very stringent. In order to meet and exceed the quality requirements, the project manager uses a set of technical guidelines, which were applied during the design phase of the project to optimize quality.

What tool or technique is the project manager using in this scenario?

a)

A Design for X (DfX) where the X in DfX represents the quality aspect of the product

b)

B Design of experiments (DOE) as a quality improvement methodology

c)

C The Manage Quality process to ensure compliance with project quality requirements

d)

D Process analysis to identify opportunities for process improvements

91.

During a status update meeting, you inform stakeholders that the project is running behind schedule but under budget. With all meeting participants in agreement, the decision is made to crash the schedule. Two weeks later, the finance director calls you stating that she just learned about the schedule issue and that she never agreed to the expense of adding project resources. When asked why she did not speak up during the meeting, the finance director replies, "What meeting?"

Which of the following most likely caused this situation?

a)

A Lack of cultural awareness

b)

B Poor conflict management skills

c)

C Inadequate meeting management

d)

D Insufficient active listening skills

92.

The resource management plan calls for six developers to serve on the project team who are all internal employees. In the process of putting together the project team, the project manager discovers that only three developers with the necessary skillset are available for the project due to attrition and higher priority projects.

What should the project manager do next?

a)

A Hire outside contractors to supplement the project team

b)

B Submit a change request to update the necessary project plans and/or documents

c)

C Cancel the project since the required resources are not available

d)

D Run the project with the three available developers and use overtime to stay on schedule

93.

You are working with your team to develop the scope management plan.

Which of the following will you need to complete this process?

a)

A Project charter and business case

b)

B Stakeholder engagement plan and quality management plan

c)

C Lessons learned register and project schedule

d)

D Project life cycle description and development approach

94.

You are a project manager leading an online conference call with stakeholders regarding project status. In the call, a few stakeholders indicate they are not sufficiently updated on project status and request a bi-weekly email be sent to them with cost and schedule status reports. You realize this request is a change in the communication requirements, which would also change the form of communication outlined in the communications management plan.

Where should you initially capture this request?

a)

A Requirements documentation

b)

B Issue log

c)

C Communications management plan

d)

D Stakeholder engagement plan

95.

You are planning a research and development project, and you need to determine how the project costs will be estimated, budgeted, managed, monitored, and controlled. To complete this process, you need to know if there are any preapproved financial resources from which the detailed project costs can be developed.

What should you do next?

a)

A Review the project charter

b)

B Consult the cost management plan

c)

C Examine the basis of estimates for the project

d)

D Check the cost baseline

96.

A vendor notifies you that they will be unable to fulfill the terms of the contract after their manufacturing plant was severely damaged by a tornado. After reviewing the contract, you inform the vendor that they will have to fulfill the agreement or face litigation.

What clause was most likely missing from the contract?

a)

A Force majeure clause

b)

B Escape clause

c)

C Arbitration clause

d)

D Gold clause

97.

A project to bring a new model of a product to market is in execution when a competitor files a lawsuit claiming that the product violates several of their patents. The courts have sided with the competitor and issued a cease and desist order.

What should the project manager do first?

a)

A Seek approval to terminate the project

b)

B Resort to alternative dispute resolution

c)

C Terminate the project for legal cause

d)

D Update the business case as necessary

98.

You have just finalized the project management plan for your project. The plan is ready to be approved.

What should you do to obtain approval?

a)

A Nothing. The project management plan does not require formal approval.

b)

B Go ahead and use your own authority as the project manager to approve the project management plan.

c)

C Request the project sponsor to approve the project management plan.

d)

D Present the project management plan to relevant stakeholders according to applicable policies and procedures

99.

You are in the process of monitoring the overall progress of project work. Throughout your project, you have experienced recurring issues, and you want your current and future projects to run more smoothly.

Which of the following is least likely to proactively promote continuous improvement?

a)

A Holding lessons learned meetings at regular intervals

b)

B Conducting retrospectives throughout the project

c)

C Periodically updating the organizational knowledge base

d)

D Timely implementing planned responses for the realized risks

100.

A project manager is executing the quality management plan of a project to manufacture a new reusable rocket to launch commercial satellites. Due to the extremely high cost of failure, the tolerances for the parts are held to a very exacting standard. The project manager has established a threshold of no more than 3.4 defects per million opportunities (DPMO).

What is the best approach to accomplish this goal?

a)

A Utilize the Three Sigma quality improvement technique

b)

B Use Six Sigma as a quality improvement methodology

c)

C Perform the Plan-do-check-act process

d)

D Design for X (DfX) is the most appropriate tool