1.

Only one person can act as Executive

a)

a. True

b)

b. False

2.

Only one person can act as Senior Supplier

a)

a. True

b)

b. False

3.

It is possible to have external Senior Supplier

a)

a. True

b)

b. False

4.

What is project OUTCOME?

a)

1. Project product

b)

2. The result of the change derived from using the project’s product

c)

3. A measurable improvement resulting from a change perceived as an advantage by one or more stakeholders

5.

What statement is INCORRECT?

a)

a. Every project has to have Project board

b)

b. Project can be closed prematurely

c)

c. Scope can be changed during the project lifecycle

d)

d. Every project has to have Executive

6.

What document captures changes?

a)

a. Daily log

b)

b. Issue register

c)

c. Project Brief

d)

d. Change Control Approach

7.

Who is most likely to be the risk owner?

a)

a. Executive

b)

b. Project manager

c)

c. Team Lead responsible for uncertainty

d)

d. CEO

8.

Who provides an administrative role in a project environment?

a)

Senior User

b)

Team manager

c)

Executive

d)

Project Support

9.

What approach guideline on how to communicate with stakeholders?

a)

Risk Management Approach

b)

Quality Management Approach

c)

Communication Management Approach

d)

Change Control Approach

10.

What document is normally a description of the main product that will be produced by the project?

a)

Project Brief

b)

Key deliverable description

c)

Scope

d)

Stage plan