Introduction to Project Management

Total questions: 10

Worksheet time: 3mins

Name
Class
Date
1.

What is the main reason that we do projects?

a)

We have free time on our hands.

b)

Make new friends.

c)

Add value to our organizations by changing the status quo.

d)

My boss wants me to do it to make his KPI better.

2.

Which is NOT part of project management process groups?

a)

Close

b)

Action

c)

Plan

d)

Initiate

3.

In the Stakeholder's map, what are we assessing the stakeholders on?

a)

Influence & Power

b)

Influence & Interest

c)

Interest & Credibility

d)

Credibility & Power

4.

Which is one of the main role of a project sponsor?

a)

Authorizes the project charter

b)

Chairs all project meetings

c)

Leads the project

d)

Collects Stakeholder's requirement

5.

Which is NOT a part of project objective statement?

a)

Scope

b)

Risk

c)

Resources / cost

d)

Schedule

6.

What is Work Breakdown Structure?

a)

A Gantt Chart with timeline

b)

Organization of project deliverables into smaller components

c)

A schedule

d)

A project charter

7.

Which of the following best describe the critical path?

a)

Tasks with the highest risk

b)

Longest time the project will take from start to finish

c)

Path with the most uncertainty

d)

Scope that is most important

8.

In risk management plan, we reduce the risk by reducing the ...

a)

budget and speed

b)

speed and impact

c)

likelihood and impact

d)

speed and scope

9.

Which of the followings is NOT a way to optimize your project?

a)

Explain the reason for not meeting the deadline

b)

Re-assign resources

c)

Do tasks concurrently

d)

Break dependencies

10.

What is the action you should take when you are given unrealistic timeline?

a)

Threatened to resign

b)

Just proceed at your own pace and ignore this requirement

c)

Show the plan with the estimated time for each task

d)

Complain to your co-workers (who doesn't vent, right?)