Site Supervision

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

Who is this refers to:

“Any employee who has the acceptable level of skills, knowledge and experience assigned to a construction site or any other such place to supervise construction work.”

a)

Project manager

b)

Site Supervisor

c)

Engineer

d)

Skill worker

2.

Which of the followings is NOT site supervisor job description?

a)

Report Progress

b)

Monitor site

c)

Record daily activities

d)

Design plan

3.

How many types of construction record are there?

a)

3

b)

4

c)

5

d)

6

4.

Ensuring that any damage caused by a contractor is accounted for and back charged accordingly if required.

This definition refers to:

a)

Inclement weather

b)

Design delays

c)

Negative variations

d)

Progress claims

5.

Being able to claim an extension of time claim with supporting diary entry reports of weather conditions and photo evidence.

This definition refers to:

a)

Inclement weather

b)

Design delays

c)

Recording safety

d)

Progress claims

6.

The progress report must be prepared and signed by:

a)

Contractor

b)

Client

c)

Superintending officer

d)

Consultant

7.

For progress report, the progress status must not exceed ______ from site meeting date.

a)

1 week

b)

3 days

c)

2 weeks

d)

1 month

8.

The frequency of site meeting depends on the:

a)

% completion

b)

Contract value

c)

Client schedule

d)

progress

9.

How many main chapter in Progress Report based on Surat Arahan Ketua Pengarah Jabatan Kerja Raya Bil.6/2015

a)

5

b)

6

c)

7

d)

8

10.

Good supervision results to:

a)

unsafe structure

b)

additional cost

c)

delay

d)

design compliance