1.

CM assumes no liability in case equipment fail to function or if a portion of the building collapses due to the deficiencies in the plans and designs that the CM participated in the review and approval.

a)

TRUE

b)

FALSE

c)

MAYBE

2.

In SPP Doc 204-B, the RPF of CM is _____ of PCC.

a)

1% to 1.5%

b)

1.5% to 3%

c)

2% to 4%

d)

2.5% to 3%

3.

The following are compensation using what contracting concepts?

- Award Fee Provisions

- Price Adjustment Provisions

- Firm Fixed Price

- Fixed Price Incentive

- Cost + Fixed Fee

- CPIF or CPAF

a)

Construction Management Contracting Concepts

b)

NOTA

c)

Construction Management

d)

AOTA

4.

Building Maintenance, Grounds & Landscaping Supervision, Building & Equipment Maintenance, and Business Dev't & Management are part/scope of what services?

a)

SPP DOC 204-A

b)

SPP DOC 204-B

c)

SPP DOC 205

d)

SPP DOC 206

5.

A service assuring that the building and all the parts thereof are all in good conditions.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

6.

A service that formulates and enforce rules for the proper use of the building and facility.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

7.

A service where they monitor security services.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

8.

A service where they monitor maintenance and upkeep services.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

9.

A service where they supervise landscape contractors and gardeners for the proper watering, pruning, trimming, and maintenance of the landscape.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

10.

A service where they maintain orderly entrances, exits and parking areas.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

11.

A service where they maintain streets.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

12.

A service where they assist the proper third parties in seeing to it tat all equipment are properly maintained and in good working conditions.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

13.

A service where they innovate schemes to attain maximum building occupancy.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

14.

A service where they bill tenants for rentals and utilities.

a)

Building Maintenance

b)

Grounds & Landscaping Supervision

c)

Building & Equipment Maintenance

d)

Business Development & Management

15.

In SPP Doc 205, the RPF based on value-pricing is from __________ of gross rentals.

a)

2% to 4%

b)

4% to 6%

c)

6% to 8%

d)

8% to 10%

16.

It refers to the range of professional services that covers:

1. Pre-design Services

2. Regular Design Services

3. Specialized Architectural Services

4. Construction Services

5. Post-Construction Services

a)

SPP DOC 205

b)

SPP DOC 206

c)

SPP DOC 207

d)

SPP DOC 208

17.

This service's over-all objective is to have control over time, cost and quality relative to the construction of a project.

a)

SPP DOC 206

b)

SPP DOC 207

c)

SPP DOC 208

d)

SPP DOC 209

18.

PM stands for _____.

a)

Project Manager

b)

Project Management

c)

AOTA

d)

NOTA

19.

They complement the functions of the Architects, Engineers, and Contractors in meeting the broad and complex requirements of projects.

a)

PM

b)

CM

c)

PiC

d)

Architect

20.

The PM should conduct regular consultations with the Owner and with the Architects and Engineers on all aspects of planning for the project during pre-construction phase.

a)

TRUE

b)

FALSE

21.

If PM serves as CM, he shall provide the services detailed under SPP Documents 204-A and/or 204-B.

a)

TRUE

b)

FALSE

22.

PM operates as a member of what team?

a)

Owner-Architect-Engineer-Contractor

b)

Owner-Architect

c)

Owner-Engineer

d)

Owner-Contractor

23.

S/He will plan, program and monitor the various activities, and will act as an adviser on material costs and construction methods.

a)

PM

b)

CM

c)

PiC

d)

Architect

24.

PM's RPF is _____ of PCC.

a)

2% to 4%

b)

2% to 5%

c)

2% to 6%

d)

2% to 8%

25.

DBS by _____ is when the various design phase services are completed, the construction phase goes beyond the periodic inspection and assessment.

a)

Administration

b)

Guaranteed Maximum Cost

c)

Owner

d)

Contractor

26.

It is the same as DBS by Administration except that it includes the guaranteed maximum project cost.

a)

Administrative

b)

Guaranteed Maximum Cost

c)

Owner

d)

Contractor

27.

In DBS on a Guaranteed Maximum Project Cost, if upon the completion of the project, there is a realized savings, this shall be divided equally between the Client and the Architect.

a)

TRUE

b)

FALSE

28.

In DBS on a Guaranteed Maximum Project Cost, the PCC shall not exceed 10% of the estimated project construction cost; otherwise, the Architect shall pay for the excess only up to the amount of his administration fee.

a)

TRUE

b)

FALSE

29.

NEDA stands for _____.

a)

National Economic and Development Authority

b)

National Economic and Development Assembly

c)

National Economic and Development Agreement

d)

Natural Economic and Development Authority

30.

In DBS, the Architect shall be a State-licensed contractor to implement his design.

a)

TRUE

b)

FALSE

31.

In DBS, if the Architect cannot request for a cash advance, what should s/he be requesting instead to the Owner?

a)

Revolving Fund

b)

Cash Fund

c)

Advance Cash

d)

Advance Fund

32.

In DBS by Administration, Architect's Fee for the Regular Design Services shall be _____ of PCC.

a)

5%

b)

6%

c)

7%

d)

8%

33.

In DBS on a Guaranteed Maximum Cost, Architect's Fee for the Regular Design Services shall be _____ of PCC or is already built-in in the Guaranteed Maximum Cost.

a)

5%

b)

10%

c)

15%

d)

20%

34.

____ may be conducted in a single-stage or 2-stage manner.

a)

Project ADCs

b)

Ideas Competition

35.

There is only one winner.

a)

Project ADCs

b)

Ideas Competition

36.

S/he assist the Jury and will be present during its deliberation but he will have no vote.

a)

Professional Advisor

b)

Advisor

c)

Professional

d)

Architect

37.

Competition of ideas set as a design and planning exercise to elucidate a problem.

a)

Project ADCs

b)

Ideas Competition

38.

S/he will supervise the conduct of ADC and prepare the conditions.

a)

Professional Advisor

b)

Professional

c)

Advisor

d)

Architect

39.

Each participant will receive honorarium if the competition is by limited invitation.

a)

TRUE

b)

FALSE

40.

In Project ADCs, winner can be the AoR is specified.

a)

TRUE

b)

FALSE

41.

In Ideas Competition, provisions shall be made in the ADC Conditions for the first prize winner to receive compensation of a further sum equal to the amount of the first prize if no contract is signed within twelve months of the announcement of the Jury's award.

a)

TRUE

b)

FALSE

42.

Professional Architect Consultant is a holder of what document?

a)

State-License for Specialization

b)

Masters Degree

c)

Doctorate Degree

43.

Compensation and allowances for PCA shall be comparable with foreign consulting service compensation standards.

a)

TRUE

b)

FALSE

44.

It used when the services of a PCA is expected to be required at intervals over a period of time.

a)

Retainer

b)

General Conditions

c)

Special Provisions

d)

Agreement

45.

What is the UAP DOC 301?

a)

Retainer

b)

General Conditions

c)

Special Provisions

d)

Agreement

46.

It is the contract between contractor and owner.

a)

Retainer

b)

General Conditions

c)

Special Provisions

d)

Agreement

47.

It stipulates procedural and administrative aspects of the contract.

a)

Retainer

b)

General Conditions

c)

Special Provisions

d)

Agreement

48.

Bid Bulletin is part of this provision.

a)

Retainer

b)

General Conditions

c)

Special Provisions

d)

Agreement

49.

It is a work of the contractor to purchase/fabricate and deliver.

a)

Furnish

b)

Install

c)

Provide

50.

It is a work of the contractor to build-in, mount in position, connect, and apply for intended use.

a)

Furnish

b)

Install

c)

Provide