1.

A Project Sponsor appointed a Project Manager to a new project and asked her

to get started immediately - even before the charter got approved. What should the

Project Manager do?

a)

Ask some project manager to take over

b)

Start critical activities

c)

Push to create and approve the chatter

d)

Start with team up and planning

2.

Which of the following is not required at the requirements elicitation and

analysis stage of an IT project management lifecycle?

a)

Interviewing users and their managers

b)

Examining documentation describing the current operations.

c)

Incentivising key stakeholders

d)

Analysing operational records created by the current system.

3.

What is referred to as the application of knowledge, skills, tools, and

techniques to project activities to meet an IT project requirement?

a)

Requirement elicitation

b)

Scope management

c)

Schedule Management

d)

IT Project Management

4.

Where a new application is to be built, the elements to be designed include all

except

a)

Input

b)

Process

c)

Requirement statement

d)

Output

5.

What most important purpose does a project chatter serve for the IT-Pmiect

Manager?

a)

Describes the cost of the project

b)

Describes the project float

c)

Describes the project scope

d)

Describe the project Process Design

6.

In identifying a business case for an IT project, what can be refer to as

feasibility report which, among other things, presents the business with a range of

options aimed at providing a solution?

a)

Project Statement of Work

b)

Deliverable

c)

Milestone Chart

d)

Project Charter

7.

In identifying a business case for an IT Project, What is referred to as the

analysis of the benefits vis-a-vis the estimated costs and the. ability of the

organisation to have the resources to pay for the investment?

a)

Technical Constraint Analysis

b)

Time Constraint Analysis

c)

Organisational Constraint Analysis

d)

Budget Constraint

8.

What determines the organization’s ability to cope with the changes that a new

IT Project Development will demand or what the project may prevent from being

developed any further

a)

Technical Constraint Analysis

b)

Time Constraint Analysis

c)

Organisational Constraint Analysis

d)

Budget Constraint Analysis

9.

Generally, IS/IT projects are formed for what objective?

a)

To take over the business as usual

b)

To ensure that the organization gains technological leadership.

c)

To solve a problem or take advantage of an opportunity.

d)

To maintain a corporate image

10.

What ordinarily distinguishes an IT project him a business as usual?

a)

Its uniqueness

b)

Its ubiquity

c)

It’s technicality

d)

Its enterprise approaches

11.

What are most information and communication technology (ICT) projects

looked on as in a business value chain?

a)

Innovation activity

b)

Support activity

c)

Technical activity

d)

Administrative activity

12.

IT Project may include all the following except

a)

Hardware Development

b)

Software development

c)

Knowledge based system

d)

Strategy development

13.

The kind of software developed from a purchased unamended commercial

package to which an additional software has been integrated to suit the user

requirement is known as

a)

A customized Software

b)

A standard off-the-shelfsoftware

c)

Bespoke Software

d)

A standard plus Software

14.

What type of software is developed to enable the end-user to complete tasks?

a)

Bespoke Software

b)

Application Software

c)

System Software

d)

Server-side software

15.

Who in the IT project management value chain champions the project at the

highest level in the company and gets rid of organizational obstructions?

a)

The IT Project Manager

b)

The IT Project Sponsor

c)

The IT Project Steering Committee

d)

The IT Project Director

16.

Who does the IT project manager receive his or her authority from?

a)

The IT Project sponsor

b)

The IT Project Team Leader

c)

The IT Project Steering Committee

d)

IT Project Stakeholders

17.

Which of the following is not one of the key roles adopted by the IT Project

Team Leader?

a)

The Boss of the IT Project

b)

Negotiator

c)

Coach

d)

Initiator

18.

The heart, as well as the true engine of the work of any IT Project, lies with

a)

The IT Project Team Leader

b)

IT Project Steering Committee

c)

IT Project Stakeholders

d)

The IT Project Team membership

19.

Dividing a development method of an IT Project into a number of processes is

a widely accepted practice in IT project management?

a)

Project Management Activities

b)

Project Gantt Chart development

c)

Project Development lifecycle

d)

Project requirements elicitation and analysis

20.

An IT Project initiation clarifies two main issues which involve

a)

Identifying Project value and the team to create it

b)

Identifying Project objectives and the requirements to achieve them

c)

Identifying Project requirements and the manager to coordinate them

d)

Identifying Project cost and the justification for funding it

21.

The term of reference that is drawn up after the business case for an IT Project is established would normally

a)

Outline the business value of the proposal and authorize staff to carry it out

b)

Outline the scope of the proposal to be investigated and authorise staff

to carry out the investigation

c)

Outline the charter of the project and authorise a project manager and

the project team to carry out the investigation

d)

Outline the scope and authority of staff to carry out the investigation

22.

If an IT Project proposal is accepted by the organisation, the project that

emerges should NOT have one of the following attributes.

a)

A defined start point

b)

A budget estimate

c)

A set of objectives

d)

A unique purpose

23.

Successful IT projects are those projects that have all the following except

a)

enable the stated objectives to be

b)

delivered with float time.

c)

deliver a system that performs to agreed specifications, including those

relating to quality.

d)

satisfy the project sponsor and other interested i.e.

stakeholders

24.

Factors that can negatively affect the success of an IT project include all the

following except

a)

Advances in technology during the project's execution

b)

Timely delivery of outcomes Within budget.

c)

Infrastructure changes that impact security and data management

d)

Unknown dependent relationships among hardware, software, network

infrastructure and data

25.

Which of the following statement is TRUE regarding the initiating process

?

a)

Initiating process group includes the development project charter and

identify stakeholders' process.

b)

Risk is lowest during the initiating process group

c)

The project has the highest profitabilityq of projoa.suooess during the

Initiating process group

d)

The project manager and the team are always identified as part of the

initiating process group

26.

Which of the following is NOT true about the project charter?

a)

It states what the project is, what the project will deliver, and how all

the processes will be managed

b)

It provides the Project Manager with the authority to assign

organisational resources

c)

It formally authorizes the project

d)

It details the business justification of the project

27.

Your project has just been completed, and one of your subcontractor has sent

you the air tickets for you and your family to have a one-month holiday in Dubai

to thank you for your business. What is the BEST way to respond?

a)

Thank the subcontractor, but do not give him preference in any future

contract .

b)

Thank the subcontractor, but politely refuse the gift

c)

Ask for tickets for the entire team, so that it is fair to everyone

d)

Report the subcontractor to BNI for investigation for attempting to

corrupt you.

28.

IT Projects have a terrible track record. In what circumstance is this statement?

a)

High prospensity to meet scope successfully

b)

High propensity to fail

c)

High propensity to be very sophisticated

d)

The high spate of incompetence among IT project managers

29.

Which of the following

may not be an advantage of using a formal IT project management process

a)

Better control of financial, physical, and human resource

b)

Shorter development times

c)

Higher cost

d)

Higher quality and increased in reliability

30.

What in IT Project Management can be described as temporary endeavor undertaken to create a unique product, service or results

a)

A project

b)

A milestone

c)

An activity

d)

A deliverable

31.

In contrast with a Project, what is described as work done to sustain the

business?

a)

An IT Project Management

b)

Operations or business as usual

c)

Business Objectives

d)

Business Process

32.

Which of the following is not an example of an IT Project?

a)

A team of students creates a Smartphone application and sells it online

b)

A company develops an innovative corporate governance model

c)

A small software development team adds a new feature to an internal

software application for the finance department

d)

A college upgrades its technology infrastructure to provide wireless

Internet access across the whole campus

33.

Which of the following cannot be classified among top contemporary strategic

technologies?

a)

Internet of things, Mobile-centrrc applications, and interfaces

b)

Contextual and social media user experience

c)

Flash drive storage devices

d)

Cloud Computing

34.

Who will usually champion an IT project idea, provides the direction, and look

for funding for the project?

a)

The Project Manager

b)

The project sponsor

c)

The Steering Committee

d)

The Project initiator

35.

Project gets strive to meet the triple constraint to avoid scope creep

What constitute the triple constraint?

a)

Time, Schedule, and Cost

b)

Scope, Cost and Time

c)

Scope, Cost and Stakeholders

d)

Quality, Cost and Scope

36.

Who responsibility is it to help their organizations make wise investment

decisions by helping to select and analyze projects from strategic perspective?

a)

Portfolio managers

b)

IT Project Manager

c)

Risk Managers

d)

Project Sponsors

37.

IT Project Management what concept is loosely defined as a set of

principles that guide our decision making based on personal values of what is

"right" and "wrong"?

a)

Policy

b)

Roster

c)

Disciplinary procedures

d)

Ethics

38.

The direction of the arrows on the lines in a PERT Chart indicates.

a)

Project manager's schedules

b)

The sequence of tasks

c)

The dependence of tasks

d)

The concurrence of tasks

39.

Most information technology systems are looked on as what activities to the

business?

a)

Business

b)

Support

c)

Primary

d)

Critical

40.

A quantitative technique used to determine how long it will take to recover the

initial investment cost of an IT project is known as...

a)

Return on Investment (ROI)

b)

Return on Capital Employed (ROCE)

c)

Net present value (NPV)

d)

Payback period