WorksheetsMid-Assessment Exam Set A
Total questions: 40
Worksheet time: 11mins
A BOM can be used for which of the following?
Costing
Material Requirement Planning
Sales and Distribution
All of the above
In SAP screen, in which screen element can you start applications directly by entering the transaction code?
Menu bar
Command Field
Title bar
Application tool bar
What is the transaction code to Change Material Master?
MM01
CS01
MM02
CR02
On transaction codes, the entry “/nex” does what?
Cancels the current transaction c
End the log-on session without a confirmation dialog box
Deletes your current session
Displays an overview of sessions
Determines which business transaction should be executed for the object that belong to the task list or order.
Control Key
Routing
Item Category
Work Center
In SAP PP, which of the following object is at the top of Organization Structure?
Plant
Company Code
Sales Organization
Storage Location
Which key field is found in Work Scheduling view?
Special Procurement Key
Production Scheduling Profile
MRP Controller
Backflush Indicator
An organizational unit allowing differentiation between various stock of a material in a plant.
Storage Location
Client
Company Code
Purchasing Organization
What is the transaction code to change BOM?
CA03
CS02
CS03
CA02
Which of the following deals with processes like demand planning, capacity levelling, material planning and production execution?
Sales and Distribution
Plant Maintenance
Finance and Controlling
Production Planning
In SAP Production Planning, how many BOMs can be created as per Material Type?
100
50
99
79
Once a department has created data for a material, the material master record exists in the database. If someone from another department wishes to enter data later, he or she does have not have to create the material master record from scratch, but only must extend the existing record by adding the information from their department.
True
False
A Work Center is a machine or group of machines where production operations are performed.
True
False
SAP PP process is related to production planning of a company and it encompasses all activities like MRP (Material Requirement Planning), BOM (Bill Of Materials), Routing, Capacity planning, etc.
True
False
Bill of Material in SAP PP is referred to a list of activities which are required to produce any material.
True
False
Routing is used for scheduling and costing of operation for raw and finished product.
True
False
In Discrete Processing, the product is not changed for a long period of time.
True
False
Production master data in production planning are performed at the company code level.
True
False
SAP PP sub modules varies as per industry type like Discrete Processing, Repetitive Process or Process Industries.
True
False
In Scheduling, you can schedule the operation in production order as per operating time in routing and formulas maintained in work center.
True
False
To create routing, it is required that you must first define work center.
True
False
Which of the following transaction code can be used to check PP tables in SAP ECC system?
SE16N
SE18
SE20
SE22
In PP, which of the following is not a valid category for BOM?
Material BOM
Equipment BOM
Costing BOM
Inspection BOM
Which of the following is not an SAP PP master data?
BOM
Material Master
Storage Location
Work Center
Planned Order can be either converted to production order or purchase requisition.
Yes
No
Maybe
Procurement Type is what identifies a material or product as make or buy item.
True
False
Procurement Type X means that material can be either purchased or produced.
True
False
Special Procurement Key 60 is for phantom assemblies.
True
False
MRP Type PD is for No Planning.
True
False
Procurement Type I is for materials which are In-house Production.
True
False
MRP Type ND is for No Planning.
True
False
Item Category L is for stock items, meaning inventory is not being kept for these materials in the warehouse.
True
False
Item Category N is for non-stock items, meaning inventory is being kept for these materials in the warehouse.
True
False
Safety Stock is considered as (-) element in MD04.
True
False
Customer Order is considered as (+) element in MD04.
True
False
Plant can only have one Storage Location assigned to it.
True
False
Plant can have multiple Storage Locations assigned to it.
True
False
Manufacturing plants can do both functions - produce and distribute goods to end customers.
True
False
Manufacturing Plants can serve as both Distribution Center and Production Plant at the same time.
True
False
Production Order is a transactional data for purchasing items to suppliers and vendors.
True
False