Inspection and testing live tests

Total questions: 36

Worksheet time: 18mins

Name
Class
Date
1.

Which of the following is the direct departure from BS7671 when a measured value of Ipf considerably exceeds those permitted for the protective devices installed at the point of test?

a)

Earth fault disconnection times will be exceeded

b)

Devices will safely interrupt the fault in time

c)

Devices will not safely interrupt the fault in time

d)

      Disconnection times will be exceeded

2.

What is the maximum permitted disconnection time for 100ma RCD to BSEN 61008 in order to meet specified time/current performance, when tested at 1xI n?

a)

40ms

b)

100ms

c)

200ms

d)

300ms

3.

Which one of the following is used to establish phase sequencing for an installation

a)

Frequency meter

b)

Power factor indicator

c)

Rotating disc instrument

d)

Earth fault loop impedance tester

4.

Which one of the following is the range tests that are carried out for RCD’s

a)

½ x I△n  – 150 x I△n

b)

½ x I△n –1 x I△n

c)

½ x I△n  – 2 x I△n – 150 x I△n   

d)

½ x I△n  – 2 x I△n – 5 x I△n 

5.

Functional tests are to be carried out on a general purpose RCD using a RCD tester. At which point during the testing process would the effectiveness of the test button on the RCD be checked.

a)

Before the instrument test

b)

Following all instrument tests

c)

Following the 0.5 X I n test but before the 1 x I△n test

d)

At no point as the instrument tests will carry out these functions

6.

The current measured between line and neutral at the origin of an electrical installation forming part of a TT system would be recorded as the

a)

Design current

b)

Nominal Current

c)

Rated current

d)

Prospective fault current

7.

The relationship between the maximum measured (Ipf) and the breaking capacity of any protective device is that the device breaking capacity is

a)

Greater than the measured Ipf

b)

Lower than the measured Ipf

c)

Lower for ring circuits

d)

Lower for radial circuits

8.

Which of the following values is recorded when verifying Ipf for a single phase circuit

a)

The lowest value from PSCC and PEFC

b)

PSCC multiplied by a factor of 2

c)

PSCC added to PEFC

d)

The higher value from PEFC and PSCC

9.

Which of the following is the correct method of measurement for PSCC for a single phase installation using two leads

a)

Using a test instrument on pfc scale between line intake and main earthing terminal

b)

Using a test instrument on pfc scale between neutral intake and main earthing terminal

c)

Using a test instrument on pfc scale between main intake line and neutral

d)

Using a test instrument on ohms scale between main intake line and neutral

10.

Which of the following is the correct method of measurement for PEFC for a single phase installation using two leads

a)

Using a test instrument on pfc scale between line intake and main earthing terminal

b)

Using a test instrument on pfc scale between neutral intake and main earthing terminal

c)

Using a test instrument on pfc scale between main intake line and neutral

d)

Using a test instrument on ohms scale between main intake line and neutral

 

11.

Which of the following is not a method of determining Ipf

a)

By calculation

b)

By enquiry

c)

By using a RCD tester

d)

By direct measurement using a EFLI tester set to measure Ipf

12.

Which of the following is the correct formula for determining Ipf by calculation

a)

Ipf = Zs/Uo

b)

Ipf = Ze/Uo

c)

Ipf = Uo/Ze

d)

Ipf = Uo/R1+R2

13.

What do the term Ze stand for

a)

Resistance of the line R1 and cpc R2 in ohms

b)

The external earth loop impedance in ohms

c)

Zs the total earth loop impedance in ohms

d)

Insulation resistance in MΩ

14.

Which of the following is the correct method of measurement for Ze for a single phase installation using two leads

a)

Using a test instrument on pfc scale between line intake and main earthing terminal

b)

Using a test instrument on pfc scale between neutral intake and main earthing terminal

c)

Using a test instrument on pfc scale between main intake line and neutral

d)

Using a EFLI tester with the means of earthing disconnected and main switch open between main intake line and disconnected main earthing conductor

15.

Which one of the following supplies would not require phase sequence testing

a)

2 wire TN-C-S

b)

3 wire TN-S

c)

4 wire TT

d)

4 wire TN-C-S

16.

Which one of the following tests would be normally carried out with test connections on the supply side of an installation main switch

a)

External earth fault loop impedance

b)

RCD operation time

c)

Insulation resistance

d)

Voltage drop

17.

Which one of the following combinations of test instruments and units display are used to establish a value of PFC.

a)

PFC tester set to KΩ

b)

PFC tester set to KA

c)

EFLI tester set to MΩ

d)

EFLI tester set to ma

18.

One part of the earth fault loop path for a TN-S system is formed by the

a)

PEN conductor

b)

Neutral conductor

c)

General mass of earth

d)

CPC

19.

Which one of the following devices is suitable for prospective fault currents in excess of 60KA

a)

BS 88

b)

BS 3036

c)

BS 1362

d)

BS EN 60898

20.

A 230v single phase circuit is protected by a 16A type B, BS EN 60898 device. Which one of the following is the minimum value of current that will cause effective disconnection in the required time, if the maximum permitted earth fault loop impedance is 2.73Ω

a)

84A

b)

90A

c)

123A

d)

160A

21.

If the breaking capacity of a BS EN 60898 protective device is given as Icn and Ics which of the following is the definition of Icn rating

a)

The current the device can disconnect but may no longer be serviceable

b)

The current of which the disconnection time will not be achieved

c)

The current the device can disconnect and remain serviceable

d)

The current of which arcing will be eliminated

22.

The type of earthing system which includes a PEN is

a)

TT

b)

TN-S

c)

TN-C-S

d)

IT

23.

The maximum tabulated earth loop impedance value for a protective device is 1.37Ω. The maximum measured value of earth loop impedance permitted for a circuit protected by this is

a)

0.961Ω

b)

1.096Ω

c)

1.370Ω

d)

2.167Ω

24.

Which one of the following is the correct location to connect test leads within an installation in order to test an RCD

a)

As close as possible to the RCD on supply side

b)

At a suitably safe location on supply side of the RCD

c)

As far away as possible from RCD on supply side

d)

At a suitably safe location on the load side of the RCD

25.

The measured value of external fault loop impedance for an installation is 0.4Ω. If the measured R1+R2 value for one of the circuits is 0.5Ω the expected Zs for the circuit is

a)

2.0Ω

b)

0.9Ω

c)

0.8Ω

d)

0.22Ω

26.

The safety precaution to be taken before disconnecting a main protective bonding conductor for testing purpose is to

a)

Warn the occupier of the premises

b)

Isolate the supply and lock off

c)

Check for parallel paths

d)

Use a screwdriver insulated 100v

27.

Insulation resistance between L-E on 230v installation gives a reading of 0.02MΩ. Which one of the following is the approximate value of current that would leak to earth during normal conditions

a)

1.5ma

b)

11.5ma

c)

1.5amps

d)

11.5amps

28.

A test of insulation resistance on a number of circuits produces the following results 10MΩ, 5MΩ, 5MΩ, 4MΩ and 2MΩ

The measured insulation resistance at the distribution board with the circuits connected in parallel will be

a)

26MΩ

b)

10MΩ

c)

5.2MΩ

d)

0.8MΩ

29.

The measured external E.F.L.I. for an installation is 0.2 ohms, if the line and cpc combined is 1.2 the expected earth fault loop impedance for the circuit will be.

a)

0.24 ohms

b)

1.0 ohms

c)

1.4 ohms

d)

3.2 ohms

30.

The external earth loop impedance is 0.6 ohms and the maximum E.F.L.I. from BS7671 for a circuit is 2.19 following any corrections what is the maximum R1+R2 to ensure fault protection.

a)

1.12 ohms

b)

1.31 ohms

c)

1.37 ohms

d)

1.59 ohms

31.

Where no supply is available a test of earth electrode resistance forming part of a TT system will be carried out using.

a)

E.F.L.I. Tester

b)

Continuity tester

c)

Earth Electrode resistance tester

d)

Low resistance ohm meter

32.

Where two copper conductors each with resistance of 0.1 ohms are connected in parallel their combined resistance will be.

a)

0.5 ohms

b)

0.2 ohms

c)

0.1 ohms

d)

0.05 ohms

33.

A check of the RCD should be recommended by pressing the RCD test button.

a)

4 weeks

b)

6 months

c)

16 months

d)

Annually

34.

The maximum test current applied to a 30ma RCD used for additional protection is.

a)

100ma

b)

150ma

c)

30ma

d)

15ma

35.

The maximum test current for 100ma RCD BS EN 61008

a)

50ma

b)

100ma

c)

150ma

d)

500ma

36.

Which one of the following is the maximum permitted disconnection time as given in BS7671 for an RCD installed to provide additional protection when tested at the maximum applied test current?

a)

30ms

b)

40ms

c)

200ms

d)

300ms