Worksheets12. Procurement Management
Total questions: 12
Worksheet time: 9mins
You are constructing an office building for your Client. You decide to outsource painting and electric work from a third party. You created a detailed work description and ask bidders to apply for this part of the Project. The document you just prepare is known as :
Procurement SoW
Request for Proposal (RFP)
Request for Information (RFI)
Project Scope Statement (PSS)
Multi-tiered structure
Cost plus award fee
Procurement audit
Request for quotation
You are managing a large Project with many Contractors working on it. A Stakeholder come to you and inform you that He never received the status report from one of your Contractor. What will your next step be?
Stop the payment and ask for clarification
Call the Contractor
Review the Communication Management Plan
Inform the Management
Due to the lack of expertise, some agile project deliverables will need to be outsourced to external vendors. The performing organization wants to ensure that the selected vendor will use agile as their delivery method to produce the contracted deliverables. What is the best course of action for the project manager?
In the source selection criteria, specify that the vendor must use agile as their project management approach
Colocate the agile project team of the performing organization with the project team of the to-be-selected vendor
Develop the deliverables in-house since this is always the best and cheapest approach to run agile projects
Select the vendor based on the best technical approach and lowest cost and set up agile training for the vendor
A key project deliverable has been outsourced to Vendor. The vendor delivered on contract, and the project manager has completed all activities associated with the Control Procurements process.
What should the Project Manager do next?
Pay vendor's invoice
Approve the deliverable received from the vendor
Conduct an Audit
Measure Stakeholder Satisfaction
As project manager for small university, you are currently in the process of selecting vendor to develop a textbook and other training material for new course. Several vendor are interested in bidding on the contract. During bidder conference, one of the prospective supplier ask about ownership of the intellectual property that will be created from the project.
Which project document should have this information at this stage of the project?
Seller Proposal
Requirement documentation
Source selection criteria
Procurement contract
You are managing a project that involves vendors. Midway into project execution, the Sponsor hands you a formal letter from the Customer informing you that your project has been terminated effective immediately. You are shocked since the project was going well and was forecasted to finish ahead of scheduled and under budget. What should you do first?
Have your attorney call the Customer's attorney
Call a meeting with the Customer
Continue doing project work until the Customer notifies you directly
Close the contracts with the vendors
You have taken over on a Project with a Vendor whre scope and requirementts have been missed. You notice miss-communication and mixed message are common. You set a meeting with your team and the Vendor's team. The meeting is extremely important to get right. What will you do next?
Speaks slowly and clearly with the Vendor's team, at a louder volume if necessary
Confirm they hear your message, determine if they agree and identified nuanced or unintended message they may have received
Only communicate with the Vendor in writing, so you have a trail of proof if anything goes wrong in the future
Prepare the claim for the mishandled scope of your project through your Procurement team.
You put together a resource plan for a large amount of physical inventory to be purchased from overseas. You ordered inventory during project execution, however global supply chain were impacted and the shipment was delayed by 3 months, significantly impacting your project. What should you have done differently?
Hire a Resource Manager to take care of the resource tasks on you rproject
Planned startegically about the timing from order to delivery usage, managing resource risk and their response
Ensured a means to track the inventory from arrival onsite to the delivery of an integrated product
Source the inventory locally to reduce the impact of global supply chains