[Intensive Odoo 1 - 12/2022] W5 - Manufacturing 1

Total questions: 22

Worksheet time: 16mins

Name
Class
Date
1.

Which statements are correct about Bill of Materials?

a)

We can set up 2 different BoMs for 1 product

b)

A BoM can contain no component line

c)

A component must be a storable or consumable product

d)

We can select both Product Template and Variant of another one in a BoM

2.

Which statements are correct about Bill of Materials?

a)

We can set up By-products for a Kit product

b)

A component could be a service product

c)

The Work Center is required when adding a new Operation

d)

The Reference must be unique

3.

In a BoM, if "Flexible Consumption" is "blocked", what will happen if the user enters the consumed qty which is greater than what is defined?

a)

Button "Validate" is hidden

b)

Only admin is able to validate the MO

c)

Odoo will raise an error when validating

d)

Odoo will raise an error when that invalid number is entered

4.

A By-Product is a (a)   product that is created during production in addition to the main product of a BoM

5.

Which work center will Odoo select when using the alternative work center feature?

a)

The current work center assigned to this work order. If it is unavailable, get from its alternative work centers

b)

The cheapest one

c)

The one which will finish the task soonest

d)

The one which has the most empty slots

6.

When will the forecasted quantity of component products be updated?

a)

When the MO is created

b)

When the MO is confirmed

c)

When the MO is in progress

d)

When the MO is ready to close

e)

When the MO is marked as done

7.

"Production" is a (an) _____ location. Its type is "_____", which consumes the components and produces finished products

a)

internal / Transit Location

b)

virtual / Production

c)

physical / Production

d)

internal / Internal Location

8.

How can we configure the Bill of Material to produce many products in the same Manufacturing Order?

a)

By creating multi-level BoM

b)

By configuring by-products

c)

Odoo does not support

d)

By setting up Alternative Product

9.

When will the stock move for finished good (Production \rightarrow WH/Stock) is created?

a)

When the MO is created

b)

When the MO is confirmed

c)

When the MO is in progress

d)

When the MO is ready to close

e)

When the MO is marked as done

10.

What is the capacity of a work center?

a)

The number of operations of a BOM it can do in parallel

b)

The number of pieces the work center can manufacture in parallel

c)

The number of workers who can work at this work center

d)

The number of MOs assigned to this work center

11.

In a quotation, there are 2 storable product items:

- Product A (quantity = 2) has 1 BoM (type is "Manufacturing this product") including 3 component lines.

- Product B (quantity = 5) has 1 BoM (type is "Kit") including 4 component lines.

How many lines are there in the Delivery Order after it is confirmed?

a)

3

b)

4

c)

7

d)

5

e)

2

12.

How many transfers will be created if the Manufacturing process is configured as 3 steps?

a)

0

b)

1

c)

2

d)

3

13.

Which statements are correct about Manufacturing Order & Product Lot/Serial Number?

a)

We can only produce exact 1 finished good in a MO if it is tracked by Lot

b)

From 1 MO, we have to create backorders if it has many items of a finished good tracked by Serial Number

c)

The Serial Number is optional if the finished good is tracked by Serial Number

d)

If the material is tracked by Serial Number, you must provide its Serial Number when consuming

14.

When a quality check is requested, can you still continue your operation without completing the quality check?

a)

Yes

b)

No

c)

Depend on the Operation Type

d)

Depend on the Quality Control type

15.

What's the purpose of Engineering Change Orders (ECO)?

a)

Create customized products based on SOs

b)

Manage BOM versions

c)

Modify a manufacturing order

16.

What does MRP stand for?

a)

Material Requirements Planning

b)

Manufacturing Ready Position

c)

Material Resources Planning

d)

Mutual Recognition Procedure

e)

Manufacturers' Recommended Price

17.

Which statements are TRUE?

a)

Cannot create MO for a service product

b)

Cannot create BoM for service product

c)

Cannot add service products into components of MO

d)

User can create a BoM including a component is the same Finished Goods

18.

Which items will be included in the Delivery Order when we confirm a SO with a Table Kit? (see the attached image to know the BoM Structure)

a)

Wood Panel, Bolt

b)

Table Kit

c)

Wood Panel, Ply Layer, Wear Layer, Bolt

d)

Ply Layer, Wear Layer, Bolt

19.

How to view the BoM cost structure of a BoM?

a)

Click on "Cost Analysis" smart button

b)

Click on "Overview" smart button

c)

Click on "Structure & Cost" smart button

d)

Click on "Manufacturing Cost" smart button

20.

Where can you generate a Quality Alert directly?

a)

Quality Control Points

b)

Quality Checks

c)

Manufacturing Orders

d)

Receipt Orders

e)

Purchase Orders/Sales Orders

21.

Which levels can you set a Quality Control Point for?

a)

Products

b)

Product Categories

c)

Operations

d)

Packages

e)

Models

22.

Choose all that apply

a)

When applying changes for an ECO with "Apply on" is Product Only , a new version of the product is created and the old version is archived

b)

When applying changes for an ECO with "Apply on" is Bill of Materials , a new version of the BoM is created and the old version is archived

c)

When start revision for an ECO with "Apply on" is Product Only , the version of the product is increased by 1

d)

When start revision for an ECO with "Apply on" is Bill of Materials , a new version of the BoM is created and archived