Worksheets[Intensive Odoo 1 - 12/2022] W5 - Manufacturing 1
Total questions: 22
Worksheet time: 16mins
Which statements are correct about Bill of Materials?
We can set up 2 different BoMs for 1 product
A BoM can contain no component line
A component must be a storable or consumable product
We can select both Product Template and Variant of another one in a BoM
Which statements are correct about Bill of Materials?
We can set up By-products for a Kit product
A component could be a service product
The Work Center is required when adding a new Operation
The Reference must be unique
In a BoM, if "Flexible Consumption" is "blocked", what will happen if the user enters the consumed qty which is greater than what is defined?
Button "Validate" is hidden
Only admin is able to validate the MO
Odoo will raise an error when validating
Odoo will raise an error when that invalid number is entered
A By-Product is a (a) product that is created during production in addition to the main product of a BoM
Which work center will Odoo select when using the alternative work center feature?
The current work center assigned to this work order. If it is unavailable, get from its alternative work centers
The cheapest one
The one which will finish the task soonest
The one which has the most empty slots
When will the forecasted quantity of component products be updated?
When the MO is created
When the MO is confirmed
When the MO is in progress
When the MO is ready to close
When the MO is marked as done
"Production" is a (an) _____ location. Its type is "_____", which consumes the components and produces finished products
internal / Transit Location
virtual / Production
physical / Production
internal / Internal Location
How can we configure the Bill of Material to produce many products in the same Manufacturing Order?
By creating multi-level BoM
By configuring by-products
Odoo does not support
By setting up Alternative Product
When will the stock move for finished good (Production → WH/Stock) is created?
When the MO is created
When the MO is confirmed
When the MO is in progress
When the MO is ready to close
When the MO is marked as done
What is the capacity of a work center?
The number of operations of a BOM it can do in parallel
The number of pieces the work center can manufacture in parallel
The number of workers who can work at this work center
The number of MOs assigned to this work center
In a quotation, there are 2 storable product items:
- Product A (quantity = 2) has 1 BoM (type is "Manufacturing this product") including 3 component lines.
- Product B (quantity = 5) has 1 BoM (type is "Kit") including 4 component lines.
How many lines are there in the Delivery Order after it is confirmed?
3
4
7
5
2
How many transfers will be created if the Manufacturing process is configured as 3 steps?
0
1
2
3
Which statements are correct about Manufacturing Order & Product Lot/Serial Number?
We can only produce exact 1 finished good in a MO if it is tracked by Lot
From 1 MO, we have to create backorders if it has many items of a finished good tracked by Serial Number
The Serial Number is optional if the finished good is tracked by Serial Number
If the material is tracked by Serial Number, you must provide its Serial Number when consuming
When a quality check is requested, can you still continue your operation without completing the quality check?
Yes
No
Depend on the Operation Type
Depend on the Quality Control type
What's the purpose of Engineering Change Orders (ECO)?
Create customized products based on SOs
Manage BOM versions
Modify a manufacturing order
What does MRP stand for?
Material Requirements Planning
Manufacturing Ready Position
Material Resources Planning
Mutual Recognition Procedure
Manufacturers' Recommended Price
Which statements are TRUE?
Cannot create MO for a service product
Cannot create BoM for service product
Cannot add service products into components of MO
User can create a BoM including a component is the same Finished Goods
Which items will be included in the Delivery Order when we confirm a SO with a Table Kit? (see the attached image to know the BoM Structure)
Wood Panel, Bolt
Table Kit
Wood Panel, Ply Layer, Wear Layer, Bolt
Ply Layer, Wear Layer, Bolt
How to view the BoM cost structure of a BoM?
Click on "Cost Analysis" smart button
Click on "Overview" smart button
Click on "Structure & Cost" smart button
Click on "Manufacturing Cost" smart button
Where can you generate a Quality Alert directly?
Quality Control Points
Quality Checks
Manufacturing Orders
Receipt Orders
Purchase Orders/Sales Orders
Which levels can you set a Quality Control Point for?
Products
Product Categories
Operations
Packages
Models
Choose all that apply
When applying changes for an ECO with "Apply on" is Product Only , a new version of the product is created and the old version is archived
When applying changes for an ECO with "Apply on" is Bill of Materials , a new version of the BoM is created and the old version is archived
When start revision for an ECO with "Apply on" is Product Only , the version of the product is increased by 1
When start revision for an ECO with "Apply on" is Bill of Materials , a new version of the BoM is created and archived