Avoid challenging stakeholders.
Make changes to the project schedule in real-time.
Ensure all stakeholders receive the same information.
Establish good working relationships with all stakeholders.
Cost
Quality assurance
Schedule
Quality customer service
Quality planning
Discuss optional stakeholder representation.
Create a communications management plan.
Set up a project team room.
Hold a project kick-off meeting.
Trust
Transparency
Honesty
Loyalty
Fast tracking
Crashing
Resource leveling
Lead and lag
Start developing the project management plan based on a previous project template from the project management office (PMO).
Conduct an impact analysis of the new initiative to determine how the project should be rolled out.
Plan a working session focusing on the scope, vision, and mission of the initiative.
Conduct benchmarking to determine the business viability of the initiative.
Create the project charter.
Conduct a kick-off meeting.
Develop the communications management plan.
Prepare and distribute the responsible, accountable, consult, and inform (RACI) matrix.
Lead a procurement meeting.
Create a work breakdown structure (WBS).
Adapt and tailor existing assets.
Sign off on the business case.
Work breakdown structure (WBS)
Work breakdown structure (WBS) dictionary
Statement of work (SOW)
Resource breakdown structure (RBS)
Request a new resource from HR.
Request a new resource from the project sponsor.
Negotiate for the resource's availability.
Tell the customer that the new change is not possible.
Eliminate the user testing from the project plan.
Utilize the current server to complete user testing.
Request to expedite the new server from the supplier.
Await the arrival of the new server and reevaluate timelines for user testing.
High Influence/Low Commitment
Low Influence/ High Commitment
Low Influence/Low Commitment
High Influence/High Commitment
Worked on different approaches of estimating to give confidence of the cost spent in each product increment.
Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies.
Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies
Worked on a fixed-price contract to switch the product owner's attention to value instead of money
Recommend that the team include risky stories in early iterations rather than later ones.
Recommend that the team choose stories with low risk for easy completion to keep team motivation high.
Work with the product owner to decide on the stories that should go during the iteration.
Use the Pareto analysis to decide which stories can be completed the fastest.
Discuss it with the project team to determine the most appropriate way to respond.
Add it to the issue log and include it in the project report.
Contact the procurement manager to expedite delivery of the material.
Escalate the issue to the project owner and request a schedule change.
Hospital radiology team
Project team
Project sponsor
Hospital procurement officer
Set up a meeting with the testing team to get more information about the testing methods to be used.
Evaluated when the mitigation strategy will be implemented to prepare for future projects.
Conducted a Monte Carlo analysis which will determine potential outcomes and responses.
Planned for these errors in the risk register as something to look for in future projects.
Ensure that a detailed user story was presented to the project team.
Have the project team implement the user story during the next sprint.
Ensure that the team performs iterative backlog refinement.
Ensure that the team recorded detailed application functionality requirements from the stakeholders.
Initiate a project risk management process to assess and mitigate the risk.
Seek expert judgment regarding the scope of the new regulations.
Consult with key stakeholders to revise the project management plan.
Start the formal change control process.
Schedule a meeting with the project team and the sponsor to clarify the scope.
Develop the project plan based on the established scope by breaking down the deliverables and requirements.
Escalate to the project management office (PMO) to clarify the unclear scope.
Submit a request to the PMO to be paired with someone familiar with the organization’s project management approach.
Initiative and intelligence
Creativity and passion
Confidence and trust
Obedience and diligence
Transfer the risks.
Update the risk register.
Request a risk audit.
Analyze the risks.
Plan a team building event where different personality types are required to solve problems.
Remind the entire team that as professionals, emotions should not impair their work performance.
Plan project tasks and meetings to avoid contact between the three members.
Avoid interfering and allow the team members time to resolve their differences.
Because the project sponsor is responsible for procuring funding and committing resources to the project
Because the project sponsor communicates directly with the customer regarding acceptance of deliverables
Because the functional managers have authority to approve project objectives but not final deliverables
Because the functional managers are too geographically dispersed to sign off on the deliverables
Schedule a meeting with the stakeholders.
Update the risk management plan.
Review the documented project requirements.
Review the final scope statement.
Ensure that the communication management plan is detailed to ensure that all stakeholders and project team members receive timely updates of project progress.
Ensure that the stakeholders and sponsor agree on the project plan, scope, and deliverables.
Implement an appropriate method for the rollout to ensure that the project focuses on the highest business value components for success.
Work closely with the marketing team to ensure that the end products align with customer communication.
Update the risk management plan to document the stakeholder’s promotion.
Monitor the stakeholder attributes and make necessary adjustments to engage the key stakeholder actively.
Reach out to the sponsor to manage stakeholder engagement.
Removed the key stakeholder from the decision-making process.
Ahead of schedule and under budget
Ahead of schedule and over budget
Behind schedule and under budget
Behind schedule and over budget
The project is behind schedule and is over budget.
The project is on schedule and is under budget.
The project is on schedule and on budget.
The project is behind schedule and under budget.
Update the communications management plan to include details about the emails and reports.
Include a formal sign-off at the end of each phase to engage the stakeholders.
Hold status meetings to solicit input from project sponsors for the emails and reports.
Update the stakeholder engagement plan at the end of each phase to maintain their commitment to the project's success.