WorksheetsProject Management Fundamentals - Module 5
Total questions: 10
Worksheet time: 5mins
Which is NOT part of S.M.A.R.T. acronym?
SPECIFIC
TECHNICAL
MEASUREABLE
ACHIEVABLE
REALISTIC
What is Estimate At Completion (EAC) at the beginning of the project?
Equal to BAC
0
Not Possible to Calculate
None of the above
What does a negative Cost Variance (CV) in Earned Value Management indicate?
Under Budget
Overbudget
On Budget
No Variance
What does a Schedule Performance Index (SPI) of 1.0 indicate in Earned Value Management?
Ahead of Schedule
On Schedule
Behind Schedule
No Schedule Variance
If the Planned Value (PV) is $80,000 and the Earned Value (EV) is $75,000, what is the Schedule Performance Index (SPI)?
0.75
0.94
1.25
1.33
Which method is NOT used to measure Stakeholder Satisfaction?
Mood Chart/Board
Net Present Value (NPV)
Turnover Rate
Net Promoter Score (NPS)
What is the primary purpose of a burndown chart in Agile project management?
Track team member workloads
Monitor project costs
Visualize progress over time
Evaluate project risks
Leading indicators are used for predective measures of (a) performance.
Which is an example of technical performance measures?
Nomber of defects fixed
Product Weight
Queue Size
Return on investment (ROI)
What does "lead time" represent in a process?
Time taken to complete a task
Time allocated for planning
Time between consecutive tasks
Time taken from request to delivery