wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Earn Value Management Quiz

Total questions: 21

Worksheet time: 11mins

Name
Class
Date
1.

What is Earned Value (EV)?

a)

Actual cost of work performed

b)

Budgeted cost of work scheduled

c)

Budgeted cost of work performed

2.

Explain the formula for Earned Value (EV).

a)

EV = % complete - BAC

b)

EV = % complete + BAC

c)

EV = % complete / BAC

d)

EV = % complete * BAC

3.

What is Planned Value (PV) in Earned Value Analysis?

a)

Actual cost of work performed

b)

Authorized budget assigned to the work scheduled to be accomplished

c)

Budget at Completion (BAC)

d)

Planned cost of work performed

4.

Define Actual Cost (AC) in the context of Earned Value Management.

a)

Planned cost for the work completed

b)

Cost budgeted for the work completed

c)

Total cost actually incurred for the work completed

d)

Estimated cost for the work completed

5.

What is the significance of Cost Performance Index (CPI) in Earned Value Analysis?

a)

It measures the scope of the project by comparing the actual work completed to the planned work

b)

It measures the cost efficiency of the project by comparing the actual cost of work performed to the budgeted cost of work performed.

c)

It measures the time efficiency of the project by comparing the actual time taken to complete the work to the estimated time

d)

It measures the quality of the project by comparing the actual quality of work performed to the expected quality

6.

Explain the concept of Schedule Performance Index (SPI) in Earned Value Management.

a)

The Schedule Performance Index (SPI) measures the quality of work in Earned Value Management.

b)

The Schedule Performance Index (SPI) measures the cost efficiency in Earned Value Management.

c)

The Schedule Performance Index (SPI) measures the risk management in Earned Value Management.

d)

The Schedule Performance Index (SPI) measures the efficiency of schedule performance in Earned Value Management.

7.

How is Earned Value Analysis used to forecast project outcomes?

a)

By guessing the project outcomes

b)

By comparing planned value, earned value, and actual cost of the project

c)

By using only the planned value

d)

By ignoring the project data

8.

Explain the concept of Variance Analysis in Earned Value Management.

a)

Analyzing the color variance in the project

b)

Comparing planned budget and schedule with actual budget and schedule

c)

Comparing actual budget with forecasted budget

d)

Measuring the temperature variance in the project

9.

Budgeted cost of work scheduled (BCWS)=Planned Value (PV)

a)

True

b)

False

10.

Budgeted cost of work performed (BCWP)= Actual Cost (AC)

a)

False

b)

True

11.

Actual cost of work performed (ACWP)=Actual Cost (AC)

a)

False

b)

True

12.

Schedule Variance, SV = EV – PV (Earned Value – Planned Value)

a)

True

b)

False

13.

Cost Variance, CV = EV –PV (Earned Value – Planned Value)

a)

False

b)

True

14.

Earned value asks and answers more important questions which are

a)

How much of the budget “should have been” spent at this point in the project?

b)

How much of the budget “have been” spent at this point in the project?

c)

•How much of the budget “must be” spent at this point in the project?

15.

The CPI is used to predict the magnitude of a possible time overrun or behind schedule. It adjusts the budget based on past performance

a)

False

b)

True

16.

The SPI is used to predict the magnitude of a possible time advance or delay. It adjusts the schedule based on past performance

a)

False

b)

True

17.

BAC= Budget at completion

a)

Actual Cost at Completion

b)

Original project estimate

18.

ETC = Estimate to Complete refers to: work that has not been performed and is therefore

an estimate cost.

a)

work that has been performed and is therefore

an actual cost.

b)

work that has not been performed and is therefore

an estimate cost.

19.

If Schedule Variance (SV) = 0

a)

the project is progressing as planned

b)

The project is behind schedule

20.

If Cost Performance Index (CPI) is less than 1.0,

a)

the earned value is more than the actual costs.

b)

indicates an over budget cost performance.

21.

If the Schedule Performance Index = 1.0,

a)

the schedule performance is behind time

b)

the schedule performance is progressing precisely as planned.