An inter-task dependency in which two tasks must finish at the same time is called :
Start-to-finish (FS)
Finish-to-start (FS)
Finish-to-finish (FF)
Start-to-start (SS)
What is the name of your instructor on Project Management Course/Subject?
Project Management Triangle consist of
Time, money, scoop
Quality, Cost, Delivery
Scope, Time, Quality
Cost, Scope, Time
PDM activities are shown in -
boxes
arrows
ADM activities are shown in -
boxes
arrows
When the cake is baked (A), it can be iced (B) is an example of -
finish-to-start (FS)
Finish-to-finish (FF)
Start-to-start (SS)
Start-to-finish (SF)
When the noon to midnight shift begins (A), the midnight to noon shift can finish (B) is an example of -
finish-to-finish (FF)
finish-to-start (FS)
start-to-start (SS)
start-to-finish (SF)
Mandatory dependencies are also called what?
soft logic
hard logic
preferred logic
An example of this activity is "you can't install windows until you have walls". What type of dependencies is this?
mandatory dependencies
discretionary dependencies
external dependencies